ITAC Assessment: OR0611
ITAC logo
ITAC Assessment: OR0611
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Sodium Hydrosulfite
NAICS 325180: Other Basic Inorganic Chemical Manufacturing
SIC 2899: Chemicals and Chemical Preparations, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 10
Plant Area 9,300
ft2
Annual Production 19,000,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $83,884 1,522,400
kWh
Electricity Demand $34,056 4,979
kW-mo/yr
Electricity Fees $1,350 -
Natural Gas $88,996 11,457
MMBtu
Other Gas $67,300 9,021
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $35,338 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (haz) Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.2621: Modify refrigeration system to operate at a lower pressure $3,437 - $3,437
62,383
kWh
- - - - -
02 2.4224: Upgrade controls on compressors $8,684 $5,600 $8,589
155,874
kWh
$95
-
kW-mo/yr
- - - -
03 2.2442: Preheat combustion air with waste heat $7,909 $37,830 - - $7,909
-
MMBtu
- - -
04 2.4321: Upgrade obsolete equipment $5,340 $11,938 $5,340
96,906
kWh
- - - - -
05 2.7135: Install occupancy sensors $2,436 $2,159 $1,793
32,522
kWh
$71
-
kW-mo/yr
- - $316 $256
06 2.2437: Recover waste heat from equipment $5,410 $3,724 - - $5,410
-
MMBtu
- - -
07 3.5215: Avoid contamination of end pieces and reuse as feed stock $1,200 $5,464 - - - $1,200
-
lb
- -
08 2.2511: Insulate bare equipment $922 $2,134 - - $922
-
MMBtu
- - -
TOTAL RECOMMENDED $35,338 $68,849 $19,159
347,685
kWh
$166
-
kW-mo/yr
$14,241
-
MMBtu
$1,200
-
lb
$316 $256
TOTAL IMPLEMENTED - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (haz) Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs