| Assessment Year | 2013 |
|---|---|
| Principal Product | Sodium Hydrosulfite |
| NAICS | 325180: Other Basic Inorganic Chemical Manufacturing |
| SIC | 2899: Chemicals and Chemical Preparations, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 10 |
| Plant Area |
9,300
ft2
|
| Annual Production | 19,000,000
lb
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Washington |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $83,884 | 1,522,400 |
kWh
|
$0.055 |
| Electricity Demand | $34,056 | 4,979 |
kW-mo/yr
|
$6.84 |
| Electricity Fees | $1,350 | - |
|
- |
| Natural Gas | $88,996 | 11,457 |
MMBtu
|
$7.77 |
| Other Gas | $67,300 | 9,021 |
MMBtu
|
$7.46 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $35,338 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.2621: Modify refrigeration system to operate at a lower pressure | $3,437 | - |
$3,437
62,383
kWh
|
- | - | - | - | - | |
| 02 | 2.4224: Upgrade controls on compressors | $8,684 | $5,600 |
$8,589
155,874
kWh
|
$95
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.2442: Preheat combustion air with waste heat | $7,909 | $37,830 | - | - |
$7,909
-
MMBtu
|
- | - | - | |
| 04 | 2.4321: Upgrade obsolete equipment | $5,340 | $11,938 |
$5,340
96,906
kWh
|
- | - | - | - | - | |
| 05 | 2.7135: Install occupancy sensors | $2,436 | $2,159 |
$1,793
32,522
kWh
|
$71
-
kW-mo/yr
|
- | - | $316 | $256 | |
| 06 | 2.2437: Recover waste heat from equipment | $5,410 | $3,724 | - | - |
$5,410
-
MMBtu
|
- | - | - | |
| 07 | 3.5215: Avoid contamination of end pieces and reuse as feed stock | $1,200 | $5,464 | - | - | - |
$1,200
-
lb
|
- | - | |
| 08 | 2.2511: Insulate bare equipment | $922 | $2,134 | - | - |
$922
-
MMBtu
|
- | - | - | |
| TOTAL RECOMMENDED | $35,338 | $68,849 |
$19,159
347,685
kWh
|
$166
-
kW-mo/yr
|
$14,241
-
MMBtu
|
$1,200
-
lb
|
$316 | $256 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs