Assessment Year | 2013 |
---|---|
Principal Product | Sodium Hydrosulfite |
NAICS | 325180: Other Basic Inorganic Chemical Manufacturing |
SIC | 2899: Chemicals and Chemical Preparations, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 10 |
Plant Area |
9,300
ft2
|
Annual Production | 19,000,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Washington |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $83,884 | 1,522,400 |
kWh
|
$0.055 |
Electricity Demand | $34,056 | 4,979 |
kW-mo/yr
|
$6.84 |
Electricity Fees | $1,350 | - |
|
- |
Natural Gas | $88,996 | 11,457 |
MMBtu
|
$7.77 |
Other Gas | $67,300 | 9,021 |
MMBtu
|
$7.46 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $35,338 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2621: Modify refrigeration system to operate at a lower pressure | $3,437 | - |
$3,437
62,383
kWh
|
- | - | - | - | - | |
02 | 2.4224: Upgrade controls on compressors | $8,684 | $5,600 |
$8,589
155,874
kWh
|
$95
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.2442: Preheat combustion air with waste heat | $7,909 | $37,830 | - | - |
$7,909
-
MMBtu
|
- | - | - | |
04 | 2.4321: Upgrade obsolete equipment | $5,340 | $11,938 |
$5,340
96,906
kWh
|
- | - | - | - | - | |
05 | 2.7135: Install occupancy sensors | $2,436 | $2,159 |
$1,793
32,522
kWh
|
$71
-
kW-mo/yr
|
- | - | $316 | $256 | |
06 | 2.2437: Recover waste heat from equipment | $5,410 | $3,724 | - | - |
$5,410
-
MMBtu
|
- | - | - | |
07 | 3.5215: Avoid contamination of end pieces and reuse as feed stock | $1,200 | $5,464 | - | - | - |
$1,200
-
lb
|
- | - | |
08 | 2.2511: Insulate bare equipment | $922 | $2,134 | - | - |
$922
-
MMBtu
|
- | - | - | |
TOTAL RECOMMENDED | $35,338 | $68,849 |
$19,159
347,685
kWh
|
$166
-
kW-mo/yr
|
$14,241
-
MMBtu
|
$1,200
-
lb
|
$316 | $256 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs