Assessment Year | 1998 |
---|---|
Principal Product | Chemicals |
NAICS |
n/a
|
SIC | 2819: Industrial Inorganic Chemicals, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 60 |
Plant Area |
97,000
ft2
|
Annual Production | 3,200,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $136,182 | 1,782,825 |
kWh
|
$0.076 |
Electricity Demand | $36,153 | 4,796 |
kW-mo/yr
|
$7.54 |
Electricity Fees | $(-13,435.0) | - |
|
- |
Natural Gas | $127,375 | 28,593 |
MMBtu
|
$4.45 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $54,196 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $23,465 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,434 | $10,179 |
$4,566
59,789
kWh
|
$868
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.2414: Use waste heat from hot flue gases to preheat | $8,097 | $5,180 | - | - |
$8,097
-
MMBtu
|
- | - | - | |
03 | 2.2136: Install / repair insulation on steam lines | $6,631 | $10,500 | - | - |
$6,631
-
MMBtu
|
- | - | - | |
04 | 4.652: Replace existing equipment with more suitable substitutes | $14,000 | $20,000 | - | - | - | - | $14,000 | - | |
05 | 4.611: Begin a practice of predictive / preventative maintenance | $9,400 | $500 | - | - | - | - | - | $9,400 | |
06 | 3.4151: Minimize water usage | $2,000 | $2,000 | - | - | - |
$2,000
-
Tgal
|
- | - | |
07 | 3.4114: Replace city water with recycled water via cooling tower | $8,634 | $5,000 |
$(-1,366.0)
(-17,878)
kWh
|
- | - |
$10,000
-
Tgal
|
- | - | |
TOTAL RECOMMENDED | $54,196 | $53,359 |
$3,200
41,911
kWh
|
$868
-
kW-mo/yr
|
$14,728
-
MMBtu
|
$12,000
-
Tgal
|
$14,000 | $9,400 | ||
TOTAL IMPLEMENTED | $23,465 | $23,179 |
$4,566
59,789
kWh
|
$868
-
kW-mo/yr
|
$6,631
-
MMBtu
|
$2,000
-
Tgal
|
- | $9,400 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs