Assessment Year | 1985 |
---|---|
Principal Product | MEAT PROCESSING |
NAICS |
n/a
|
SIC | 2013: Sausages and Other Prepared Meat Products |
Sales Range | $10 M to 50M |
# of Employees | 130 |
Plant Area |
n/a
|
Annual Production | 300,000
lb
|
Production Hrs. Annual | 2,210
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $165,645 | 3,358,148 |
kWh
|
$0.049 |
Natural Gas | $43,542 | 8,831 |
MMBtu
|
$4.93 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $9,838 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,791 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,180 | $2,587 |
$1,180
24,033
kWh
|
- | |
02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,791 | $300 | - |
$2,791
-
MMBtu
|
|
03 | 2.7261: Install timers and/or thermostats | $1,650 | $142 |
$117
2,345
kWh
|
$1,533
-
MMBtu
|
|
04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $3,847 | $400 |
$3,847
-
kWh
|
- | |
05 | 2.3512: De-energize excess transformer capacity | $253 | $100 |
$253
5,275
kWh
|
- | |
06 | 2.4221: Install compressor air intakes in coolest locations | $117 | $100 |
$117
2,345
kWh
|
- | |
TOTAL RECOMMENDED | $9,838 | $3,629 |
$5,514
33,998
kWh
|
$4,324
-
MMBtu
|
||
TOTAL IMPLEMENTED | $2,791 | $300 | - |
$2,791
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs