| Assessment Year | 1985 |
|---|---|
| Principal Product | ANALYSIS EQUIPMENT |
| NAICS |
n/a
|
| SIC | 3829: Measuring and Controlling Devices, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 350 |
| Plant Area |
n/a
|
| Annual Production | 30,000
pieces
|
| Production Hrs. Annual | 4,940
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $188,191 | 2,410,023 |
kWh
|
$0.078 |
| Natural Gas | $20,522 | 4,292 |
MMBtu
|
$4.78 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $7,670 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $6,936 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.6232: Install set-back timers | $2,302 | $300 |
$2,302
29,601
kWh
|
- | |
| 02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,018 | $100 | - |
$1,018
-
MMBtu
|
|
| 03 | 2.1222: Install turbulators | $518 | $300 | - |
$518
-
MMBtu
|
|
| 04 | 2.4221: Install compressor air intakes in coolest locations | $216 | $400 |
$216
2,931
kWh
|
- | |
| 05 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $3,616 | $2,800 |
$3,616
-
kWh
|
- | |
| TOTAL RECOMMENDED | $7,670 | $3,900 |
$6,134
32,532
kWh
|
$1,536
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $6,936 | $3,200 |
$5,918
29,601
kWh
|
$1,018
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs