ITAC Assessment: CO0017
ITAC logo
ITAC Assessment: CO0017
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1985
Principal Product ANALYSIS EQUIPMENT
NAICS
n/a
SIC 3829: Measuring and Controlling Devices, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 350
Plant Area
n/a
Annual Production 30,000
pieces
Production Hrs. Annual 4,940
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $188,191 2,410,023
kWh
Natural Gas $20,522 4,292
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $7,670 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,936

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.6232: Install set-back timers $2,302 $300 $2,302
29,601
kWh
-
02 2.1233: Analyze flue gas for proper air/fuel ratio $1,018 $100 - $1,018
-
MMBtu
03 2.1222: Install turbulators $518 $300 - $518
-
MMBtu
04 2.4221: Install compressor air intakes in coolest locations $216 $400 $216
2,931
kWh
-
05 2.3131: Reschedule plant operations or reduce load to avoid peaks $3,616 $2,800 $3,616
-
kWh
-
TOTAL RECOMMENDED $7,670 $3,900 $6,134
32,532
kWh
$1,536
-
MMBtu
TOTAL IMPLEMENTED $6,936 $3,200 $5,918
29,601
kWh
$1,018
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs