Assessment Year | 1984 |
---|---|
Principal Product | PRINTED CIRCUIT BOARDS |
NAICS |
n/a
|
SIC | 3679: Electronic Components, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
n/a
|
Annual Production | 730,000
pieces
|
Production Hrs. Annual | 2,210
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $91,852 | 1,565,944 |
kWh
|
$0.059 |
Natural Gas | $24,335 | 4,961 |
MMBtu
|
$4.91 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $32,387 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $32,387 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,286 | $600 |
$5,286
89,977
kWh
|
- | |
02 | 2.3191: Use demand controller or load shedder | $3,583 | $500 |
$3,583
-
kWh
|
- | |
03 | 2.3512: De-energize excess transformer capacity | $409 | $600 |
$409
7,034
kWh
|
- | |
04 | 2.1233: Analyze flue gas for proper air/fuel ratio | $3,186 | $400 | - |
$3,186
-
MMBtu
|
|
05 | 2.7441: Replace broken windows and/or window sash | $1,101 | $6 |
$29
293
kWh
|
$1,072
-
MMBtu
|
|
06 | 2.7261: Install timers and/or thermostats | $16,597 | $4,000 |
$10,297
175,557
kWh
|
$6,300
-
MMBtu
|
|
07 | 2.7422: Plant trees or shrubs near windows to shield from sunlight | $1,984 | $1,160 |
$1,984
33,705
kWh
|
- | |
08 | 2.6212: Turn off equipment during breaks, reduce operating time | $241 | $17 |
$28
293
kWh
|
$213
-
MMBtu
|
|
TOTAL RECOMMENDED | $32,387 | $7,283 |
$21,616
306,859
kWh
|
$10,771
-
MMBtu
|
||
TOTAL IMPLEMENTED | $32,387 | $7,283 |
$21,616
306,859
kWh
|
$10,771
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs