ITAC Assessment: CO0006
ITAC logo
ITAC Assessment: CO0006
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1984
Principal Product FABRICATED STEEL
NAICS
n/a
SIC 3441: Fabricated Structural Metal
Sales Range $10
M
to 50
M
# of Employees 65
Plant Area
n/a
Annual Production 7,000
ton
Production Hrs. Annual 4,000
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $19,434 284,291
kWh
Natural Gas $9,973 2,044
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $5,272 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,564

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $350 $300 $350
5,275
kWh
-
02 2.1233: Analyze flue gas for proper air/fuel ratio $105 $300 - $105
-
MMBtu
03 2.4231: Reduce the pressure of compressed air to the minimum required $356 $20 $356
5,275
kWh
-
04 2.7492: Use proper thickness of insulation on building envelope $820 $1,939 - $820
-
MMBtu
05 2.2437: Recover waste heat from equipment $288 $150 - $288
-
MMBtu
06 2.3131: Reschedule plant operations or reduce load to avoid peaks $2,708 $5,000 $2,708
29,601
kWh
-
07 2.7261: Install timers and/or thermostats $347 $125 $86
2,638
kWh
$261
-
MMBtu
08 2.3521: Reduce load on electrical conductor to reduce heating losses $134 $200 $134
2,052
kWh
-
09 2.4221: Install compressor air intakes in coolest locations $164 $60 $164
2,345
kWh
-
TOTAL RECOMMENDED $5,272 $8,094 $3,798
47,186
kWh
$1,474
-
MMBtu
TOTAL IMPLEMENTED $2,564 $3,094 $1,090
17,585
kWh
$1,474
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs