Assessment Year | 1997 |
---|---|
Principal Product | Rugs |
NAICS |
n/a
|
SIC | 2273: Carpets and Rugs |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
90,600
ft2
|
Annual Production | 2,500,000
lb
|
Production Hrs. Annual | 2,000
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $38,491 | 699,883 |
kWh
|
$0.055 |
Electricity Demand | $30,497 | 3,490 |
kW-mo/yr
|
$8.74 |
Electricity Fees | $4,101 | - |
|
- |
Natural Gas | $157,000 | 34,948 |
MMBtu
|
$4.49 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $226,760 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,136 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2136: Install / repair insulation on steam lines | $980 | $2,000 | - | - | - |
$980
-
MMBtu
|
- | - | - | - | - | |
02 | 2.2135: Repair and eliminate steam leaks | $3,470 | $1,200 | - | - | - |
$3,470
-
MMBtu
|
- | - | - | - | - | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $94 | $240 |
$46
879
kWh
|
$42
-
kW-mo/yr
|
$6 | - | - | - | - | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,626 | $300 |
$794
14,361
kWh
|
$755
-
kW-mo/yr
|
$77 | - | - | - | - | - | - | |
05 | 2.7111: Reduce illumination to minimum necessary levels | $1,060 | $632 |
$517
9,379
kWh
|
$493
-
kW-mo/yr
|
$50 | - | - | - | - | - | - | |
06 | 3.4151: Minimize water usage | $533 | - | - | - | - |
$102
-
MMBtu
|
$87
-
Tgal
|
- | $276 |
$68
-
Tgal
|
- | |
07 | 3.4111: Use closed cycle process to minimize waste water production | $4,999 | $3,200 | - | - | - |
$1,476
-
MMBtu
|
$714
-
Tgal
|
- | $2,256 |
$553
-
Tgal
|
- | |
08 | 4.652: Replace existing equipment with more suitable substitutes | $207,108 | $330,000 | - | - | - |
$54,525
-
MMBtu
|
$20,433
-
Tgal
|
- | $105,150 | - | $27,000 | |
09 | 2.8114: Change rate schedules or other changes in utility service | $6,890 | - | - | - | - | - | - | $6,890 | - | - | - | |
TOTAL RECOMMENDED | $226,760 | $337,572 |
$1,357
24,619
kWh
|
$1,290
-
kW-mo/yr
|
$133 |
$60,553
-
MMBtu
|
$21,234
-
Tgal
|
$6,890 | $107,682 |
$621
-
Tgal
|
$27,000 | ||
TOTAL IMPLEMENTED | $7,136 | $4,132 |
$1,311
23,740
kWh
|
$1,248
-
kW-mo/yr
|
$127 |
$4,450
-
MMBtu
|
- | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs