ITAC Assessment: GT0622
ITAC logo
ITAC Assessment: GT0622
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Rugs
NAICS
n/a
SIC 2273: Carpets and Rugs
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 90,600
ft2
Annual Production 2,500,000
lb
Production Hrs. Annual 2,000
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $38,491 699,883
kWh
Electricity Demand $30,497 3,490
kW-mo/yr
Electricity Fees $4,101 -
Natural Gas $157,000 34,948
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $226,760 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,136

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings Ancillary Material Cost Savings Water Consumption Savings Increase in Production Savings
01 2.2136: Install / repair insulation on steam lines $980 $2,000 - - - $980
-
MMBtu
- - - - -
02 2.2135: Repair and eliminate steam leaks $3,470 $1,200 - - - $3,470
-
MMBtu
- - - - -
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $94 $240 $46
879
kWh
$42
-
kW-mo/yr
$6 - - - - - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,626 $300 $794
14,361
kWh
$755
-
kW-mo/yr
$77 - - - - - -
05 2.7111: Reduce illumination to minimum necessary levels $1,060 $632 $517
9,379
kWh
$493
-
kW-mo/yr
$50 - - - - - -
06 3.4151: Minimize water usage $533 - - - - $102
-
MMBtu
$87
-
Tgal
- $276 $68
-
Tgal
-
07 3.4111: Use closed cycle process to minimize waste water production $4,999 $3,200 - - - $1,476
-
MMBtu
$714
-
Tgal
- $2,256 $553
-
Tgal
-
08 4.652: Replace existing equipment with more suitable substitutes $207,108 $330,000 - - - $54,525
-
MMBtu
$20,433
-
Tgal
- $105,150 - $27,000
09 2.8114: Change rate schedules or other changes in utility service $6,890 - - - - - - $6,890 - - -
TOTAL RECOMMENDED $226,760 $337,572 $1,357
24,619
kWh
$1,290
-
kW-mo/yr
$133 $60,553
-
MMBtu
$21,234
-
Tgal
$6,890 $107,682 $621
-
Tgal
$27,000
TOTAL IMPLEMENTED $7,136 $4,132 $1,311
23,740
kWh
$1,248
-
kW-mo/yr
$127 $4,450
-
MMBtu
- - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings Ancillary Material Cost Savings Water Consumption Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs