| Assessment Year | 2023 |
|---|---|
| Principal Product | Commercial Real Estate Management |
| NAICS | 531312: Nonresidential Property Managers |
| SIC | 6512: Operators of Nonresidential Buildings |
| Sales Range | $1 M to 5M |
| # of Employees | 2 |
| Plant Area |
85,700
ft2
|
| Annual Production | 80,000
units
|
| Production Hrs. Annual | 2,600
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $10,521 | 137,168 |
kWh
|
$0.077 | |
| Electricity Demand | $6,658 | 344 |
kW-mo/yr
|
$19.35 | |
| Electricity Fees | $5,560 | - |
|
- | |
| Natural Gas | $32,637 | 2,902 |
MMBtu
|
$11.25 | |
| Waste Disposal Costs | |||||
| Water Usage | $4,726 | 503 |
Tgal
|
$9.40 | |
| TOTAL YEARLY COSTS | $60,102 | ||||
| RECOMMENDED SAVINGS* | $33,927 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $31,889 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4322: Use or replace with energy efficient substitutes | $1,503 | $1,627 |
$830
10,820
kWh
|
$673
-
kW-mo/yr
|
- | - | |
| 02 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $29,223 | $819,000 | - | - |
$29,223
-
MMBtu
|
- | |
| 03 | 2.7261: Install timers and/or thermostats | $1,163 | $8,685 | - | - |
$1,163
-
MMBtu
|
- | |
| 04 | 2.7444: Close holes and openings in building such as broken windows | $290 | $2,349 | - | - |
$290
-
MMBtu
|
- | |
| 05 | 2.2622: Replace existing chiller with high efficiency model | $1,748 | - | - | - | - | $1,748 | |
| TOTAL RECOMMENDED | $33,927 | $831,661 |
$830
10,820
kWh
|
$673
-
kW-mo/yr
|
$30,676
-
MMBtu
|
$1,748 | ||
| TOTAL IMPLEMENTED | $31,889 | $829,312 |
$830
10,820
kWh
|
$673
-
kW-mo/yr
|
$30,386
-
MMBtu
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs