ITAC Assessment: CM1020
ITAC logo
ITAC Assessment: CM1020
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Commercial Real Estate Management
NAICS 531312: Nonresidential Property Managers
SIC 6512: Operators of Nonresidential Buildings
Sales Range $1
M
to 5
M
# of Employees 2
Plant Area 85,700
ft2
Annual Production 80,000
units
Production Hrs. Annual 2,600
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $10,521 137,168
kWh
Electricity Demand $6,658 344
kW-mo/yr
Electricity Fees $5,560 -
Natural Gas $32,637 2,902
MMBtu
Waste Disposal Costs
Water Usage $4,726 503
Tgal
TOTAL YEARLY COSTS $60,102
RECOMMENDED SAVINGS* $33,927 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $31,889

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
01 2.4322: Use or replace with energy efficient substitutes $1,503 $1,627 $830
10,820
kWh
$673
-
kW-mo/yr
- -
02 2.7491: Insulate glazing, walls, ceilings, and roofs $29,223 $819,000 - - $29,223
-
MMBtu
-
03 2.7261: Install timers and/or thermostats $1,163 $8,685 - - $1,163
-
MMBtu
-
04 2.7444: Close holes and openings in building such as broken windows $290 $2,349 - - $290
-
MMBtu
-
05 2.2622: Replace existing chiller with high efficiency model $1,748 - - - - $1,748
TOTAL RECOMMENDED $33,927 $831,661 $830
10,820
kWh
$673
-
kW-mo/yr
$30,676
-
MMBtu
$1,748
TOTAL IMPLEMENTED $31,889 $829,312 $830
10,820
kWh
$673
-
kW-mo/yr
$30,386
-
MMBtu
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs