Assessment Year | 2023 |
---|---|
Principal Product | Aircraft Parts Maintenance |
NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 43 |
Plant Area |
18,000
ft2
|
Annual Production | 8,000
pieces
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $67,397 | 429,858 |
kWh
|
$0.16 | |
Electricity Demand | $19,797 | 3,496 |
kW-mo/yr
|
$5.66 | |
Electricity Fees | $11,610 | - |
|
- | |
Natural Gas | $4,285 | 147 |
MMBtu
|
$29.15 | |
Waste Disposal Costs | |||||
Water Usage | $12,359 | 1,252 |
Tgal
|
$9.87 | |
Water Disposal | $9,075 | 1,252 |
Tgal
|
$7.25 | |
TOTAL YEARLY COSTS | $124,523 | ||||
RECOMMENDED SAVINGS* | $135,971 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Usage Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.9114: Use solar heat to make electricty | $70,514 | $548,740 |
$66,235
422,415
kWh
|
$4,279
-
kW-mo/yr
|
- | - | |
02 | 2.7447: Install vinyl strip / high speed / air curtain doors | $42,450 | $24,000 |
$11,250
71,744
kWh
|
- | - | $31,200 | |
03 | 2.6231: Utilize controls to operate equipment only when needed | $10,792 | $2,500 |
$10,792
68,826
kWh
|
- | - | - | |
04 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $6,992 | $8,890 |
$6,992
44,591
kWh
|
- | - | - | |
05 | 2.1321: Replace fossil fuel equipment with electrical equipment | $1,769 | $3,500 |
$1,769
11,283
kWh
|
- | - | - | |
06 | 2.6212: Turn off equipment during breaks, reduce operating time | $1,444 | $200 |
$1,444
9,210
kWh
|
- | - | - | |
07 | 2.4322: Use or replace with energy efficient substitutes | $1,159 | $1,500 | - | - |
$1,159
-
Tgal
|
- | |
08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $851 | $1,500 |
$776
4,951
kWh
|
$75
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $135,971 | $590,830 |
$99,258
633,020
kWh
|
$4,354
-
kW-mo/yr
|
$1,159
-
Tgal
|
$31,200 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Usage Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs