ITAC Assessment: BD0423
ITAC logo
ITAC Assessment: BD0423
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Industrial coatings
NAICS 325510: Paint and Coating Manufacturing
SIC 2851: Paints, Varnishes, Lacquers, Enamels, and Allied Products
Sales Range $10
M
to 50
M
# of Employees 140
Plant Area 74,225
ft2
Annual Production 3,800
Tgal
Production Hrs. Annual 4,160
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $144,062 3,403,027
kWh
Electricity Demand $53,541 8,354
kW-mo/yr
Electricity Fees $10,023 -
Natural Gas $53,179 10,188
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $105,956 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $24,347

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 2.4221: Install compressor air intakes in coolest locations $26,430 $2,000 $26,175
614,425
kWh
$256
-
kW-mo/yr
- - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $12,499 $18,273 $9,893
211,383
kWh
$2,606
-
kW-mo/yr
- - -
03 2.4226: Use / purchase optimum sized compressor $6,135 $100,000 $4,700
110,325
kWh
$1,435
-
kW-mo/yr
- - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $4,565 $4,565 $3,613
77,194
kWh
$952
-
kW-mo/yr
- - -
05 2.4231: Reduce the pressure of compressed air to the minimum required $1,616 $20 $1,221
20,018
kWh
$395
-
kW-mo/yr
- - -
06 2.7135: Install occupancy sensors $3,795 $9,000 $3,111
73,033
kWh
$684
-
kW-mo/yr
- - -
07 2.7447: Install vinyl strip / high speed / air curtain doors $3,404 $2,000 - - $3,404
-
MMBtu
- -
08 2.2414: Use waste heat from hot flue gases to preheat $838 $3,250 $(-68.0)
(-1,600)
kWh
$(-38.0)
-
kW-mo/yr
$944
-
MMBtu
- -
09 2.2437: Recover waste heat from equipment $975 $1,500 - - $975
-
MMBtu
- -
10 2.1222: Install turbulators $543 $115 - - $543
-
MMBtu
- -
11 2.2136: Install / repair insulation on steam lines $173 $250 - - $173
-
MMBtu
- -
12 3.8141: Regenerate cleaning solvent on-site and reuse $44,983 $302,000 $(-892.0)
(-14,623)
kWh
- - $58,375
-
lb
$(-12,500.0)
TOTAL RECOMMENDED $105,956 $442,973 $47,753
1,090,155
kWh
$6,290
-
kW-mo/yr
$6,039
-
MMBtu
$58,375
-
lb
$(-12,500.0)
TOTAL IMPLEMENTED $24,347 $124,588 $18,206
398,902
kWh
$4,993
-
kW-mo/yr
$1,148
-
MMBtu
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs