Assessment Year | 2001 |
---|---|
Principal Product | Custom molded plastic parts |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 25 |
Plant Area |
28,850
ft2
|
Annual Production | 81,000,000
pieces
|
Production Hrs. Annual | 6,600
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $85,592 | 2,430,720 |
kWh
|
$0.035 |
Electricity Demand | $45,285 | 6,004 |
kW-mo/yr
|
$7.54 |
Electricity Fees | $2,531 | - |
|
- |
LPG | $9,418 | 597 |
MMBtu
|
$15.78 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $14,296 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Disposal Savings | Other Liquid (haz) Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2511: Insulate bare equipment | $1,548 | $503 |
$1,525
45,889
kWh
|
- | $23 | - | - | |
02 | 2.7135: Install occupancy sensors | $208 | $215 |
$205
6,167
kWh
|
- | $3 | - | - | |
03 | 2.7261: Install timers and/or thermostats | $180 | $236 |
$177
5,338
kWh
|
- | $3 | - | - | |
04 | 2.7228: Avoid introducing hot, humid, or dirty air into hvac system | $9,552 | $3,309 |
$7,401
222,723
kWh
|
$2,010
-
kW-mo/yr
|
$141 | - | - | |
05 | 2.7122: Disconnect ballasts | $571 | $160 |
$268
8,064
kWh
|
$295
-
kW-mo/yr
|
$8 | - | - | |
06 | 3.6124: Burn waste oil for heat | $2,078 | $4,461 | - | - | - | - |
$2,078
-
gal
|
|
07 | 4.812: Apply for investment incentives | $159 | $50 | - | - | - |
$159
-
Tgal
|
- | |
TOTAL RECOMMENDED | $14,296 | $8,934 |
$9,576
288,181
kWh
|
$2,305
-
kW-mo/yr
|
$178 |
$159
-
Tgal
|
$2,078
-
gal
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Disposal Savings | Other Liquid (haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs