| Assessment Year | 2012 |
|---|---|
| Principal Product | Polymer polishing pads |
| NAICS | 334416: Capacitor, Resistor, Coil, Transformer, and Other Inductor Manufacturing |
| SIC | 3674: Semiconductors and Related Devices |
| Sales Range | $10 M to 50M |
| # of Employees | 70 |
| Plant Area |
40,227
ft2
|
| Annual Production | 72,000
pieces
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $172,449 | 2,302,023 |
kWh
|
$0.075 |
| Electricity Demand | $30,135 | 5,164 |
kW-mo/yr
|
$5.84 |
| Electricity Fees | $3,482 | - |
|
- |
| Natural Gas | $19,934 | 2,671 |
MMBtu
|
$7.46 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $19,911 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $6,287 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7447: Install vinyl strip / high speed / air curtain doors | $3,209 | $12,000 | - | - |
$3,209
-
MMBtu
|
- | - | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $5,063 | $3,690 |
$4,403
58,789
kWh
|
$660
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,599 | $3,696 |
$2,958
39,489
kWh
|
$641
-
kW-mo/yr
|
- | - | - | - | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $2,421 | $300 |
$1,937
25,861
kWh
|
$484
-
kW-mo/yr
|
- | - | - | - | |
| 05 | 2.7135: Install occupancy sensors | $1,935 | $2,100 |
$1,313
17,537
kWh
|
$622
-
kW-mo/yr
|
- | - | - | - | |
| 06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,398 | $20 |
$1,212
16,176
kWh
|
$186
-
kW-mo/yr
|
- | - | - | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $753 | $500 |
$449
5,992
kWh
|
$48
-
kW-mo/yr
|
- | - | $112 | $144 | |
| 08 | 2.3137: Use power during off-peak periods | $555 | $20 | - |
$555
-
kW-mo/yr
|
- | - | - | - | |
| 09 | 3.4114: Replace city water with recycled water via cooling tower | $978 | $1,200 |
$(-7.0)
(-93)
kWh
|
$(-7.0)
-
kW-mo/yr
|
- |
$1,192
-
Tgal
|
$(-200.0) | - | |
| TOTAL RECOMMENDED | $19,911 | $23,526 |
$12,265
163,751
kWh
|
$3,189
-
kW-mo/yr
|
$3,209
-
MMBtu
|
$1,192
-
Tgal
|
$(-88.0) | $144 | ||
| TOTAL IMPLEMENTED | $6,287 | $6,296 |
$4,720
63,018
kWh
|
$1,311
-
kW-mo/yr
|
- | - | $112 | $144 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs