| Assessment Year | 2012 |
|---|---|
| Principal Product | Heat and serve entrees |
| NAICS | 311991: Perishable Prepared Food Manufacturing |
| SIC | 2099: Food Preparations, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 85 |
| Plant Area |
30,578
ft2
|
| Annual Production | 85,000,000
lb
|
| Production Hrs. Annual | 3,756
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $107,931 | 2,361,263 |
kWh
|
$0.046 |
| Electricity Demand | $26,623 | 5,913 |
kW-mo/yr
|
$4.50 |
| Electricity Fees | $23,944 | - |
|
- |
| Natural Gas | $72,818 | 9,970 |
MMBtu
|
$7.30 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $101,161 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $14,632 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7447: Install vinyl strip / high speed / air curtain doors | $31,639 | $4,573 |
$28,831
630,868
kWh
|
- | - | $2,808 | - | |
| 02 | 2.2437: Recover waste heat from equipment | $15,397 | $800 | - | - |
$15,397
-
MMBtu
|
- | - | |
| 03 | 2.1213: Direct warmest air to combustion intake | $12,730 | $10,000 | - | - |
$12,730
-
MMBtu
|
- | - | |
| 04 | 2.2414: Use waste heat from hot flue gases to preheat | $8,394 | $3,000 | - | - |
$8,394
-
MMBtu
|
- | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,151 | $7,591 |
$3,156
69,083
kWh
|
$995
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,404 | $500 |
$2,999
65,611
kWh
|
$405
-
kW-mo/yr
|
- | - | - | |
| 07 | 2.4234: Cool compressor air intake with heat exchanger | $2,394 | $9,400 |
$2,192
32,675
kWh
|
$202
-
kW-mo/yr
|
- | - | - | |
| 08 | 2.4133: Use most efficient type of electric motors | $2,126 | $3,350 |
$1,616
35,354
kWh
|
$510
-
kW-mo/yr
|
- | - | - | |
| 09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,962 | $2,736 |
$1,460
31,938
kWh
|
$502
-
kW-mo/yr
|
- | - | - | |
| 10 | 2.7135: Install occupancy sensors | $1,808 | $1,350 |
$1,227
26,859
kWh
|
$581
-
kW-mo/yr
|
- | - | - | |
| 11 | 2.1222: Install turbulators | $772 | $1,500 | - | - |
$772
-
MMBtu
|
- | - | |
| 12 | 2.4221: Install compressor air intakes in coolest locations | $434 | $150 |
$332
7,256
kWh
|
$103
-
kW-mo/yr
|
- | - | - | |
| 13 | 2.4231: Reduce the pressure of compressed air to the minimum required | $254 | $10 |
$193
4,223
kWh
|
$61
-
kW-mo/yr
|
- | - | - | |
| 14 | 3.4115: Recover and reuse cooling water | $15,696 | $2,200 | - | - | - | - |
$15,696
-
Tgal
|
|
| TOTAL RECOMMENDED | $101,161 | $47,160 |
$42,005
903,867
kWh
|
$3,359
-
kW-mo/yr
|
$37,293
-
MMBtu
|
$2,808 |
$15,696
-
Tgal
|
||
| TOTAL IMPLEMENTED | $14,632 | $6,360 |
$4,419
96,693
kWh
|
$1,047
-
kW-mo/yr
|
$9,166
-
MMBtu
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs