ITAC Assessment: BD0381
ITAC logo
ITAC Assessment: BD0381
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2010
Principal Product Mining and Aggregate Parts
NAICS 331524: Aluminum Foundries (except Die-Casting)
SIC 3369: Nonferrous Foundries, Except Aluminum and Copper
Sales Range $50
M
to 100
M
# of Employees 180
Plant Area 164,784
ft2
Annual Production 5,821,157
lb
Production Hrs. Annual 5,824
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $445,442 7,146,430
kWh
Electricity Demand $59,678 24,442
kW-mo/yr
Electricity Fees $93,627 -
Natural Gas $140,399 16,191
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $110,184 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $45,505

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $40,618 $24,140 $38,319
457,263
kWh
$2,299
-
kW-mo/yr
- - -
02 2.7447: Install vinyl strip / high speed / air curtain doors $24,197 $70,000 - - $12,297
-
MMBtu
$11,900 -
03 2.7231: Use radiant heater for spot heating $17,856 $30,000 - - $17,856
-
MMBtu
- -
04 2.4231: Reduce the pressure of compressed air to the minimum required $14,634 $40 $13,834
159,114
kWh
$800
-
kW-mo/yr
- - -
05 2.4314: Use synthetic lubricant $5,789 $2,000 $5,789
69,080
kWh
- - - -
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,137 $2,500 $1,526
18,206
kWh
$611
-
kW-mo/yr
- - -
07 2.7135: Install occupancy sensors $2,065 $1,350 $1,922
22,937
kWh
$143
-
kW-mo/yr
- - -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $1,069 $725 $697
8,322
kWh
$28
-
kW-mo/yr
- $144 $200
09 2.7142: Utilize higher efficiency lamps and/or ballasts $812 $2,060 $766
9,139
kWh
$46
-
kW-mo/yr
- - -
10 2.4133: Use most efficient type of electric motors $591 $1,900 $422
5,036
kWh
$169
-
kW-mo/yr
- - -
11 2.4221: Install compressor air intakes in coolest locations $416 $600 $358
5,865
kWh
$58
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $110,184 $135,315 $63,633
754,962
kWh
$4,154
-
kW-mo/yr
$30,153
-
MMBtu
$12,044 $200
TOTAL IMPLEMENTED $45,505 $78,575 $19,167
222,754
kWh
$1,797
-
kW-mo/yr
$12,297
-
MMBtu
$12,044 $200
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs