| Assessment Year | 2006 |
|---|---|
| Principal Product | Screen-printed aluminum signs |
| NAICS | 323113: Commercial Screen Printing |
| SIC | 3993: Signs and Advertising Specialties |
| Sales Range | $10 M to 50M |
| # of Employees | 85 |
| Plant Area |
145,500
ft2
|
| Annual Production | 2,000,000
lb
|
| Production Hrs. Annual | 2,730
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $92,086 | 1,804,329 |
kWh
|
$0.051 |
| Electricity Demand | $13,445 | 6,352 |
kW-mo/yr
|
$2.12 |
| Natural Gas | $211,535 | 21,523 |
MMBtu
|
$9.83 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $67,711 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $66,191 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.1221: Replace obsolete burners with more efficient ones | $26,169 | $32,500 | - | - |
$26,169
-
MMBtu
|
|
| 02 | 2.1213: Direct warmest air to combustion intake | $6,891 | $4,000 | - | - |
$6,891
-
MMBtu
|
|
| 03 | 2.7261: Install timers and/or thermostats | $15,291 | $1,368 | - | - |
$15,291
-
MMBtu
|
|
| 04 | 2.7231: Use radiant heater for spot heating | $13,127 | $27,572 | - | - |
$13,127
-
MMBtu
|
|
| 05 | 2.7444: Close holes and openings in building such as broken windows | $424 | $237 | - | - |
$424
-
MMBtu
|
|
| 06 | 2.7135: Install occupancy sensors | $2,979 | $1,350 |
$2,518
50,863
kWh
|
$461
-
kW-mo/yr
|
- | |
| 07 | 2.4133: Use most efficient type of electric motors | $1,520 | $4,820 |
$1,189
24,024
kWh
|
$331
-
kW-mo/yr
|
- | |
| 08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,310 | $900 |
$1,103
22,287
kWh
|
$207
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $67,711 | $72,747 |
$4,810
97,174
kWh
|
$999
-
kW-mo/yr
|
$61,902
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $66,191 | $67,927 |
$3,621
73,150
kWh
|
$668
-
kW-mo/yr
|
$61,902
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs