ITAC Assessment: KU0432
ITAC logo
ITAC Assessment: KU0432
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Pasta
NAICS
n/a
SIC 2098: Macaroni, Spaghetti, Vermicelli, and Noodles
Sales Range $50
M
to 100
M
# of Employees 90
Plant Area 62,000
ft2
Annual Production 81,600,000
lb
Production Hrs. Annual 8,160
hrs
Location (State) Nebraska

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $154,027 4,317,116
kWh
Natural Gas $65,120 22,405
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $26,111 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $15,456

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Personnel Changes Savings
01 3.1191: Change procedures / equipment / operating conditions $8,499 $1,000 $(-2,280.0)
(-63,892)
kWh
$10,779
-
MMBtu
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $3,954 $12,296 $3,954
110,785
kWh
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $701 $1,328 $701
19,637
kWh
- -
04 2.7135: Install occupancy sensors $1,015 $850 $1,015
28,429
kWh
- -
05 3.2176: Increase use of automation $3,426 $1,000 $(-42.0)
(-1,172)
kWh
- $3,468
06 2.4226: Use / purchase optimum sized compressor $2,605 - $2,605
72,978
kWh
- -
07 2.4221: Install compressor air intakes in coolest locations $1,141 $250 $1,141
31,946
kWh
- -
08 2.4133: Use most efficient type of electric motors $4,770 $11,382 $4,770
133,646
kWh
- -
TOTAL RECOMMENDED $26,111 $28,106 $11,864
332,357
kWh
$10,779
-
MMBtu
$3,468
TOTAL IMPLEMENTED $15,456 $26,006 $11,988
335,874
kWh
- $3,468
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs