ITAC Assessment: BD0249
ITAC logo
ITAC Assessment: BD0249
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Pumpkin Puree
NAICS 311421: Fruit and Vegetable Canning
SIC 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies
Sales Range $1
M
to 5
M
# of Employees 130
Plant Area 169,000
ft2
Annual Production 161,280
ton
Production Hrs. Annual 2,880
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $164,526 3,064,807
kWh
Electricity Demand $26,916 11,521
kW-mo/yr
Natural Gas $716,809 152,275
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $327,484 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $230,189

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
01 2.2135: Repair and eliminate steam leaks $106,883 $3,200 - - $106,883
-
MMBtu
- - - -
02 2.2135: Repair and eliminate steam leaks $73,616 $4,000 - - $73,616
-
MMBtu
- - - -
03 2.1222: Install turbulators $20,715 $4,800 - - $20,715
-
MMBtu
- - - -
04 2.1231: Establish burner maintenance schedule for boilers $13,506 $250 - - $13,506
-
MMBtu
- - - -
05 2.2437: Recover waste heat from equipment $11,077 $20,000 $1,538
28,647
kWh
$105
-
kW-mo/yr
$7,584
-
MMBtu
$1,850
-
Tgal
- - -
06 2.2511: Insulate bare equipment $7,951 $6,000 - - $7,951
-
MMBtu
- - - -
07 2.1213: Direct warmest air to combustion intake $6,325 $3,000 - - $6,325
-
MMBtu
- - - -
08 2.4133: Use most efficient type of electric motors $5,173 $12,250 $4,952
92,255
kWh
$221
-
kW-mo/yr
- - - - -
09 2.7134: Use photocell controls $3,218 $225 $2,655
49,454
kWh
$272
-
kW-mo/yr
- - $85 $206 -
10 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,791 $1,200 $2,633
49,044
kWh
$158
-
kW-mo/yr
- - - - -
11 2.7142: Utilize higher efficiency lamps and/or ballasts $2,262 $6,120 $1,638
28,388
kWh
$191
-
kW-mo/yr
- - $26 $407 -
12 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,672 $660 $1,599
29,743
kWh
$73
-
kW-mo/yr
- - - - -
13 2.7135: Install occupancy sensors $950 $1,200 $756
13,435
kWh
$95
-
kW-mo/yr
- - $11 $88 -
14 2.6231: Utilize controls to operate equipment only when needed $885 $200 $834
15,531
kWh
$51
-
kW-mo/yr
- - - - -
15 2.4231: Reduce the pressure of compressed air to the minimum required $755 - $712
13,264
kWh
$43
-
kW-mo/yr
- - - - -
16 2.7111: Reduce illumination to minimum necessary levels $575 $24 $440
7,570
kWh
$36
-
kW-mo/yr
- - $6 $93 -
17 2.7144: Install spectral reflectors / delamp $294 $335 $189
3,330
kWh
$10
-
kW-mo/yr
- - $15 $80 -
18 2.4221: Install compressor air intakes in coolest locations $274 $500 $252
4,700
kWh
$22
-
kW-mo/yr
- - - - -
19 3.4113: Treat and reuse rinse waters $29,980 $10,000 - - - $29,980
-
Tgal
- - -
20 3.4151: Minimize water usage $11,992 - - - - $11,992
-
Tgal
- - -
21 4.441: Install automatic packing equipment $22,695 $99,000 - - - - $22,695 - -
22 4.821: Pay bills on time to avoid late fees $2,256 - - - - - - - $2,256
23 4.447: Automate payroll system $1,639 $2,500 - - - - $1,639 - -
TOTAL RECOMMENDED $327,484 $175,464 $18,198
335,361
kWh
$1,277
-
kW-mo/yr
$236,580
-
MMBtu
$43,822
-
Tgal
$24,477 $874 $2,256
TOTAL IMPLEMENTED $230,189 $43,960 $11,967
222,730
kWh
$766
-
kW-mo/yr
$201,589
-
MMBtu
$13,842
-
Tgal
$1,739 $286 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs