ITAC Assessment: BD0240
ITAC logo
ITAC Assessment: BD0240
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Steel Wires
NAICS 331222: Steel Wire Drawing
SIC 3315: Steel Wiredrawing and Steel Nails and Spikes
Sales Range $10
M
to 50
M
# of Employees 90
Plant Area 94,500
ft2
Annual Production 94,350
ton
Production Hrs. Annual 7,488
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $592,592 16,280,000
kWh
Electricity Demand $2,685 23,971
kW-mo/yr
Natural Gas $554,392 148,406
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $344,869 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $42,091

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (haz) Savings Personnel Changes Savings Primary Raw Material Savings
01 2.2442: Preheat combustion air with waste heat $24,677 $4,000 - - $24,677
-
MMBtu
- - - -
02 2.2136: Install / repair insulation on steam lines $16,799 $33,005 - - $16,799
-
MMBtu
- - - -
03 2.7111: Reduce illumination to minimum necessary levels $14,062 $750 $13,008
357,357
kWh
$64
-
kW-mo/yr
- - - $550 $440
04 2.4133: Use most efficient type of electric motors $10,092 $22,130 $10,024
257,357
kWh
$68
-
kW-mo/yr
- - - - -
05 2.4221: Install compressor air intakes in coolest locations $8,436 $1,000 $8,395
230,630
kWh
$41
-
kW-mo/yr
- - - - -
06 2.4239: Eliminate or reduce compressed air usage $7,033 $7,500 $7,015
192,718
kWh
$18
-
kW-mo/yr
- - - - -
07 2.2437: Recover waste heat from equipment $5,367 $14,000 - - $5,367
-
MMBtu
- - - -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $4,474 $1,250 $3,960
108,780
kWh
$19
-
kW-mo/yr
- - - $45 $450
09 2.4231: Reduce the pressure of compressed air to the minimum required $4,368 - $4,347
119,434
kWh
$21
-
kW-mo/yr
- - - - -
10 2.4111: Utilize energy-efficient belts and other improved mechanisms $4,111 $500 $4,106
112,782
kWh
$5
-
kW-mo/yr
- - - - -
11 2.7134: Use photocell controls $3,929 $1,250 $3,407
93,584
kWh
$43
-
kW-mo/yr
- - - $45 $434
12 2.7142: Utilize higher efficiency lamps and/or ballasts $2,951 $452 $1,752
48,132
kWh
$8
-
kW-mo/yr
- - - $690 $501
13 2.7135: Install occupancy sensors $1,894 $675 $1,424
39,140
kWh
$8
-
kW-mo/yr
- - - $231 $231
14 3.1161: Eliminate/reduce an operation $33,260 - - - - - $33,260
-
lb
- -
15 3.4151: Minimize water usage $14,330 $400 - - - $14,330
-
Tgal
- - -
16 4.445: Install equipment to move product $149,760 $40,000 - - - - - $149,760 -
17 4.446: Automate finishing process $38,182 $54,800 - - - - - $38,182 -
18 4.447: Automate payroll system $1,144 $2,500 - - - - - $1,144 -
TOTAL RECOMMENDED $344,869 $184,212 $57,438
1,559,914
kWh
$295
-
kW-mo/yr
$46,843
-
MMBtu
$14,330
-
Tgal
$33,260
-
lb
$190,647 $2,056
TOTAL IMPLEMENTED $42,091 $42,155 $10,422
286,302
kWh
$61
-
kW-mo/yr
$16,799
-
MMBtu
$14,330
-
Tgal
- $45 $434
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (haz) Savings Personnel Changes Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs