ITAC Assessment: BD0122
ITAC logo
ITAC Assessment: BD0122
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Outdoor Storage Lockers and Buildings
NAICS
n/a
SIC 3448: Prefabricated Metal Buildings and Components
Sales Range $5
M
to 10
M
# of Employees 60
Plant Area 89,000
ft2
Annual Production 1,000
pieces
Production Hrs. Annual 2,730
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $18,284 526,964
kWh
Electricity Demand $29,095 2,352
kW-mo/yr
Electricity Fees $673 -
Natural Gas $16,519 3,179
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $89,330 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,598

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $4,044 $12,900 $1,746
50,410
kWh
$2,298
-
kW-mo/yr
- - - - -
02 2.7231: Use radiant heater for spot heating $3,315 $7,200 - - $3,315
-
MMBtu
- - - -
03 2.7135: Install occupancy sensors $2,196 $1,350 $825
23,740
kWh
$1,371
-
kW-mo/yr
- - - - -
04 2.2437: Recover waste heat from equipment $1,934 $750 - - $1,934
-
MMBtu
- - - -
05 2.4221: Install compressor air intakes in coolest locations $351 $250 $137
3,810
kWh
$214
-
kW-mo/yr
- - - - -
06 2.2123: Insulate feedwater tank $56,279 $15,800 - - - $56,279
-
gal
- - -
07 3.5315: Lease / purchase baler; sell cardboard to recycler $8,070 $8,000 - - - - $8,070
-
lb
- -
08 4.446: Automate finishing process $12,828 $25,000 - - - - - $12,828 -
09 4.821: Pay bills on time to avoid late fees $313 - - - - - - - $313
TOTAL RECOMMENDED $89,330 $71,250 $2,708
77,960
kWh
$3,883
-
kW-mo/yr
$5,249
-
MMBtu
$56,279
-
gal
$8,070
-
lb
$12,828 $313
TOTAL IMPLEMENTED $2,598 $1,000 $137
3,810
kWh
$214
-
kW-mo/yr
$1,934
-
MMBtu
- - - $313
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs