Assessment Year | 1998 |
---|---|
Principal Product | Outdoor Storage Lockers and Buildings |
NAICS |
n/a
|
SIC | 3448: Prefabricated Metal Buildings and Components |
Sales Range | $5 M to 10M |
# of Employees | 60 |
Plant Area |
89,000
ft2
|
Annual Production | 1,000
pieces
|
Production Hrs. Annual | 2,730
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $18,284 | 526,964 |
kWh
|
$0.035 |
Electricity Demand | $29,095 | 2,352 |
kW-mo/yr
|
$12.37 |
Electricity Fees | $673 | - |
|
- |
Natural Gas | $16,519 | 3,179 |
MMBtu
|
$5.20 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $89,330 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,598 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,044 | $12,900 |
$1,746
50,410
kWh
|
$2,298
-
kW-mo/yr
|
- | - | - | - | - | |
02 | 2.7231: Use radiant heater for spot heating | $3,315 | $7,200 | - | - |
$3,315
-
MMBtu
|
- | - | - | - | |
03 | 2.7135: Install occupancy sensors | $2,196 | $1,350 |
$825
23,740
kWh
|
$1,371
-
kW-mo/yr
|
- | - | - | - | - | |
04 | 2.2437: Recover waste heat from equipment | $1,934 | $750 | - | - |
$1,934
-
MMBtu
|
- | - | - | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $351 | $250 |
$137
3,810
kWh
|
$214
-
kW-mo/yr
|
- | - | - | - | - | |
06 | 2.2123: Insulate feedwater tank | $56,279 | $15,800 | - | - | - |
$56,279
-
gal
|
- | - | - | |
07 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $8,070 | $8,000 | - | - | - | - |
$8,070
-
lb
|
- | - | |
08 | 4.446: Automate finishing process | $12,828 | $25,000 | - | - | - | - | - | $12,828 | - | |
09 | 4.821: Pay bills on time to avoid late fees | $313 | - | - | - | - | - | - | - | $313 | |
TOTAL RECOMMENDED | $89,330 | $71,250 |
$2,708
77,960
kWh
|
$3,883
-
kW-mo/yr
|
$5,249
-
MMBtu
|
$56,279
-
gal
|
$8,070
-
lb
|
$12,828 | $313 | ||
TOTAL IMPLEMENTED | $2,598 | $1,000 |
$137
3,810
kWh
|
$214
-
kW-mo/yr
|
$1,934
-
MMBtu
|
- | - | - | $313 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs