ITAC Assessment: BD0095
ITAC logo
ITAC Assessment: BD0095
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Metal Stampings
NAICS
n/a
SIC 3499: Fabricated Metal Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 100,000
ft2
Annual Production 2,000,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $39,851 383,646
kWh
Electricity Demand $46,835 3,854
kW-mo/yr
Electricity Fees $12,298 -
Natural Gas $8,197 2,345
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $286,936 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $14,145

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings Primary Product Savings
01 2.2437: Recover waste heat from equipment $5,163 $1,500 - - $5,163
-
MMBtu
- - -
02 2.4133: Use most efficient type of electric motors $4,013 $7,630 $2,202
64,771
kWh
$1,811
-
kW-mo/yr
- - - -
03 2.1123: Install automatic stack damper $3,211 $700 - - $3,211
-
MMBtu
- - -
04 2.7447: Install vinyl strip / high speed / air curtain doors $2,717 $1,500 - - $2,717
-
MMBtu
- - -
05 2.7135: Install occupancy sensors $1,553 $225 $950
27,843
kWh
$603
-
kW-mo/yr
- - - -
06 2.4314: Use synthetic lubricant $1,349 $300 $646
19,050
kWh
$703
-
kW-mo/yr
- - - -
07 2.7314: Reduce ventilation air $1,321 $1,000 - - $1,321
-
MMBtu
- - -
08 2.4221: Install compressor air intakes in coolest locations $1,319 $800 $690
20,223
kWh
$629
-
kW-mo/yr
- - - -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $699 $1,201 $334
9,965
kWh
$365
-
kW-mo/yr
- - - -
10 2.1222: Install turbulators $281 $502 - - $281
-
MMBtu
- - -
11 3.5316: Contract a wood pallet recycling company $5,430 $420 - - - - $5,430 -
12 3.5315: Lease / purchase baler; sell cardboard to recycler $750 $400 - - - $750
-
lb
- -
13 4.122: Develop standard procedures to improve internal yields $259,130 $240,900 - - - - - $259,130
TOTAL RECOMMENDED $286,936 $257,078 $4,822
141,852
kWh
$4,111
-
kW-mo/yr
$12,693
-
MMBtu
$750
-
lb
$5,430 $259,130
TOTAL IMPLEMENTED $14,145 $12,056 $3,486
102,579
kWh
$2,779
-
kW-mo/yr
$7,880
-
MMBtu
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs