ITAC Assessment: BD0029
ITAC logo
ITAC Assessment: BD0029
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Steel Fabricators
NAICS
n/a
SIC 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 35
Plant Area 26,416
ft2
Annual Production 833
ton
Production Hrs. Annual 2,042
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $37,667 535,463
kWh
Natural Gas $4,558 892
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $8,523 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,231

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Primary Raw Material Savings
01 2.7447: Install vinyl strip / high speed / air curtain doors $29 $126 - $29
-
MMBtu
-
02 2.2531: Re-size charging openings or add movable cover or door $1,170 $2,100 - $1,170
-
MMBtu
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $297 $679 $297
4,103
kWh
- -
04 2.7111: Reduce illumination to minimum necessary levels $1,326 $135 $1,326
18,757
kWh
- -
05 2.7135: Install occupancy sensors $182 $350 $182
2,638
kWh
- -
06 2.4221: Install compressor air intakes in coolest locations $1,244 $200 $1,244
17,585
kWh
- -
07 2.4322: Use or replace with energy efficient substitutes $288 $700 - - $288
08 2.4133: Use most efficient type of electric motors $3,987 $4,500 $3,987
56,565
kWh
- -
TOTAL RECOMMENDED $8,523 $8,790 $7,036
99,648
kWh
$1,199
-
MMBtu
$288
TOTAL IMPLEMENTED $5,231 $4,700 $5,231
74,150
kWh
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs