ITAC Assessment: AT0005
ITAC logo
ITAC Assessment: AT0005
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1985
Principal Product FURNITURE HARDWARE
NAICS
n/a
SIC 3429: Hardware, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 145
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 2,080
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $152,153 2,919,988
kWh
Natural Gas $253,110 47,748
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $34,248 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $33,902

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4133: Use most efficient type of electric motors $490 $1,183 $490
9,379
kWh
-
02 2.1233: Analyze flue gas for proper air/fuel ratio $5,390 $300 - $5,390
-
MMBtu
03 2.4221: Install compressor air intakes in coolest locations $291 $400 $291
5,569
kWh
-
04 2.7312: Minimize use of outside make-up air for ventilation except when used for economizer cycle $3,384 $226 $1,661
31,946
kWh
$1,723
-
MMBtu
05 2.7111: Reduce illumination to minimum necessary levels $346 - $346
6,741
kWh
-
06 2.7261: Install timers and/or thermostats $24,347 $1,200 - $24,347
-
MMBtu
TOTAL RECOMMENDED $34,248 $3,309 $2,788
53,635
kWh
$31,460
-
MMBtu
TOTAL IMPLEMENTED $33,902 $3,309 $2,442
46,894
kWh
$31,460
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs