Assessment Year | 2024 |
---|---|
Principal Product | Refrigerated produce |
NAICS | 493120: Refrigerated Warehousing and Storage |
SIC | 4222: Refrigerated Warehousing and Storage |
Sales Range | $1 M to 5M |
# of Employees | 17 |
Plant Area |
80,000
ft2
|
Annual Production | 5,000,000
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $105,769 | 1,033,871 |
kWh
|
$0.10 | |
Electricity Demand | $20,072 | 3,066 |
kW-mo/yr
|
$6.55 | |
Electricity Fees | $19,971 | - |
|
- | |
Waste Disposal Costs | |||||
Water Usage | $3,092 | 5,053 |
Tgal
|
$0.61 | |
Water Disposal | $3,926 | 5,685 |
Tgal
|
$0.69 | |
TOTAL YEARLY COSTS | $152,830 | ||||
RECOMMENDED SAVINGS* | $4,130 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,471 | $579 |
$294
2,877
kWh
|
$15
-
kW-mo/yr
|
- | $1,162 | |
02 | 2.7135: Install occupancy sensors | $1,253 | $1,182 |
$1,215
11,880
kWh
|
$38
-
kW-mo/yr
|
- | - | |
03 | 2.8114: Change rate schedules or other changes in utility service | $569 | $810 | - | - | $569 | - | |
04 | 2.7226: Use computer programs to optimize hvac performance | $258 | $472 |
$258
2,527
kWh
|
- | - | - | |
05 | 2.7444: Close holes and openings in building such as broken windows | $248 | $187 |
$248
2,431
kWh
|
- | - | - | |
06 | 2.6231: Utilize controls to operate equipment only when needed | $194 | $162 |
$194
1,892
kWh
|
- | - | - | |
07 | 2.7272: Install heat pipes / raise cooling setpoint | $137 | $22 |
$137
1,341
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $4,130 | $3,414 |
$2,346
22,948
kWh
|
$53
-
kW-mo/yr
|
$569 | $1,162 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs