Assessment Year | 2022 |
---|---|
Principal Product | Aerospace components |
NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
Sales Range | $100 M to 500M |
# of Employees | 350 |
Plant Area |
243,000
ft2
|
Annual Production | 11,500
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $529,992 | 7,326,400 |
kWh
|
$0.072 |
Electricity Demand | $77,418 | 15,096 |
kW-mo/yr
|
$5.13 |
Electricity Fees | $14,836 | - |
|
- |
TOTAL YEARLY COSTS | $622,246 | |||
RECOMMENDED SAVINGS* | $84,126 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $22,298 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $47,690 | $126,497 |
$44,451
614,808
kWh
|
$3,239
-
kW-mo/yr
|
- | - | |
02 | 2.1321: Replace fossil fuel equipment with electrical equipment | $11,446 | $48,382 |
$(-1,260.0)
(-17,422)
kWh
|
- |
$12,706
-
gal
|
- | |
03 | 2.2515: Use optimum thickness insulation | $10,522 | $15,516 |
$8,916
123,335
kWh
|
$1,606
-
kW-mo/yr
|
- | - | |
04 | 2.4226: Use / purchase optimum sized compressor | $8,331 | $39,600 |
$7,593
105,026
kWh
|
$738
-
kW-mo/yr
|
- | - | |
05 | 2.6231: Utilize controls to operate equipment only when needed | $2,692 | $2,880 |
$2,462
34,055
kWh
|
$230
-
kW-mo/yr
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,189 | $859 |
$1,986
27,472
kWh
|
$115
-
kW-mo/yr
|
- | $88 | |
07 | 2.4221: Install compressor air intakes in coolest locations | $1,256 | $1,541 |
$1,145
15,841
kWh
|
$111
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $84,126 | $235,275 |
$65,293
903,115
kWh
|
$6,039
-
kW-mo/yr
|
$12,706
-
gal
|
$88 | ||
TOTAL IMPLEMENTED | $22,298 | $57,516 |
$19,640
271,674
kWh
|
$2,570
-
kW-mo/yr
|
- | $88 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs