| Assessment Year | 2000 |
|---|---|
| Principal Product | Acrylic Spas |
| NAICS |
n/a
|
| SIC | 3088: Plastics Plumbing Fixtures |
| Sales Range | $10 M to 50M |
| # of Employees | 130 |
| Plant Area |
80,000
ft2
|
| Annual Production | 10,000
pieces
|
| Production Hrs. Annual | 2,678
hrs
|
| Location (State) | Arizona |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $124,172 | 1,997,948 |
kWh
|
$0.062 |
| Electricity Demand | $21,466 | 7,999 |
kW-mo/yr
|
$2.68 |
| Electricity Fees | $8,838 | - |
|
- |
| Natural Gas | $11,660 | 1,687 |
MMBtu
|
$6.91 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $70,831 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $63,547 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,105 | $3,527 |
$795
14,361
kWh
|
$310
-
kW-mo/yr
|
- | - | - | - | - | |
| 02 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $449 | $240 |
$449
8,206
kWh
|
- | - | - | - | - | - | |
| 03 | 2.7261: Install timers and/or thermostats | $474 | $525 |
$474
8,499
kWh
|
- | - | - | - | - | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,403 | $140 |
$3,007
54,807
kWh
|
$1,396
-
kW-mo/yr
|
- | - | - | - | - | |
| 05 | 2.4133: Use most efficient type of electric motors | $593 | $1,365 |
$405
7,327
kWh
|
$188
-
kW-mo/yr
|
- | - | - | - | - | |
| 06 | 3.6192: Use a less expensive method of waste removal | $13,808 | $90 | - | - | - |
$13,808
-
lb
|
- | - | - | |
| 07 | 3.5217: Reuse / recycle/ sell paper products | $575 | $60 | - | - | - |
$575
-
lb
|
- | - | - | |
| 08 | 3.6192: Use a less expensive method of waste removal | $370 | $170 | - | - |
$370
-
gal
|
- | - | - | - | |
| 09 | 4.812: Apply for investment incentives | $1,545 | $60 | - | - | - | - | - | $1,545 | - | |
| 10 | 4.231: Purchase equipment instead of leasing | $3,240 | $12,060 | - | - | - | - | - | $3,240 | - | |
| 11 | 4.652: Replace existing equipment with more suitable substitutes | $44,269 | $150,000 | - | - | - |
$522
-
lb
|
$19,272 | - | $24,475 | |
| TOTAL RECOMMENDED | $70,831 | $168,237 |
$5,130
93,200
kWh
|
$1,894
-
kW-mo/yr
|
$370
-
gal
|
$14,905
-
lb
|
$19,272 | $4,785 | $24,475 | ||
| TOTAL IMPLEMENTED | $63,547 | $152,120 |
$3,886
70,633
kWh
|
$1,584
-
kW-mo/yr
|
- |
$14,330
-
lb
|
$19,272 | - | $24,475 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs