ITAC Assessment: AS0226
ITAC logo
ITAC Assessment: AS0226
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Synthetic Stucco Products
NAICS
n/a
SIC 2899: Chemicals and Chemical Preparations, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 22
Plant Area 22,000
ft2
Annual Production 11,000,000
lb
Production Hrs. Annual 3,850
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $38,402 572,098
kWh
Electricity Demand $6,261 2,368
kW-mo/yr
Electricity Fees $2,417 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $16,714 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $13,677

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Solid Waste (non-haz) Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,695 $6,794 $2,067
37,808
kWh
$628
-
kW-mo/yr
- - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $200 $236 $143
2,638
kWh
$57
-
kW-mo/yr
- - - -
03 2.4133: Use most efficient type of electric motors $2,756 $7,072 $2,002
36,635
kWh
$754
-
kW-mo/yr
- - - -
04 2.7261: Install timers and/or thermostats $251 $75 $251
4,689
kWh
- - - - -
05 2.4231: Reduce the pressure of compressed air to the minimum required $3,554 $60 $2,614
48,066
kWh
$940
-
kW-mo/yr
- - - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $342 $212 $254
4,689
kWh
$88
-
kW-mo/yr
- - - -
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $3,126 $620 $2,300
42,204
kWh
$826
-
kW-mo/yr
- - - -
08 3.1191: Change procedures / equipment / operating conditions $1,203 $30 - - - $1,303
-
lb
- $(-100.0)
09 4.231: Purchase equipment instead of leasing $1,827 $625 - - $(-11.0)
-
Tgal
- $1,973 $(-135.0)
10 4.821: Pay bills on time to avoid late fees $760 $60 - - - - $760 -
TOTAL RECOMMENDED $16,714 $15,784 $9,631
176,729
kWh
$3,293
-
kW-mo/yr
$(-11.0)
-
Tgal
$1,303
-
lb
$2,733 $(-235.0)
TOTAL IMPLEMENTED $13,677 $8,778 $7,310
134,232
kWh
$2,577
-
kW-mo/yr
$(-11.0)
-
Tgal
$1,303
-
lb
$2,733 $(-235.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Solid Waste (non-haz) Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs