| Assessment Year | 1995 |
|---|---|
| Principal Product | Plastic Injection Molds and Moldings |
| NAICS |
n/a
|
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $100 M to 500M |
| # of Employees | 850 |
| Plant Area |
177,000
ft2
|
| Annual Production | 1,750,000
pieces
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Arizona |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $862,090 | 14,304,514 |
kWh
|
$0.060 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $121,592 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $19,702 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
|---|---|---|---|---|---|
| 01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,774 | - |
$4,774
84,994
kWh
|
|
| 02 | 2.4237: Substitute compressed air cooling with water or air cooling | $6,377 | $1,210 |
$6,377
90,563
kWh
|
|
| 03 | 2.7261: Install timers and/or thermostats | $2,635 | $3,000 |
$2,635
56,272
kWh
|
|
| 04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,601 | $13,858 |
$3,601
66,530
kWh
|
|
| 05 | 2.4133: Use most efficient type of electric motors | $45,737 | $33,737 |
$45,737
835,873
kWh
|
|
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $5,916 | - |
$5,916
106,975
kWh
|
|
| 07 | 2.6231: Utilize controls to operate equipment only when needed | $16,477 | $1,472 |
$16,477
351,407
kWh
|
|
| 08 | 2.2511: Insulate bare equipment | $6,627 | $19,576 |
$6,627
121,336
kWh
|
|
| 09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $27,645 | $70,488 |
$27,645
484,467
kWh
|
|
| 10 | 2.7134: Use photocell controls | $1,803 | $600 |
$1,803
38,394
kWh
|
|
| TOTAL RECOMMENDED | $121,592 | $143,941 |
$121,592
2,236,811
kWh
|
||
| TOTAL IMPLEMENTED | $19,702 | $4,210 |
$19,702
338,804
kWh
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs