ITAC Assessment: AS0096
ITAC logo
ITAC Assessment: AS0096
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product ELECTRICAL POWER EQUIP.
NAICS
n/a
SIC 3679: Electronic Components, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 215
Plant Area
n/a
Annual Production 20,000,000
pieces
Production Hrs. Annual 4,550
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $229,181 2,643,904
kWh
Natural Gas $11,577 2,020
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $23,541 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,330

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7131: Add area lighting switches $1,219 $2,012 $1,219
14,068
kWh
02 2.7111: Reduce illumination to minimum necessary levels $2,441 - $2,441
28,136
kWh
03 2.4133: Use most efficient type of electric motors $369 $497 $369
4,396
kWh
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $628 - $628
7,327
kWh
05 2.7233: Use properly designed and sized hvac equipment $4,006 $7,200 $4,006
46,307
kWh
06 2.2614: Use cooling tower or economizer to replace chiller cooling $8,455 $9,000 $8,455
97,597
kWh
07 2.6231: Utilize controls to operate equipment only when needed $516 $200 $516
5,862
kWh
08 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $909 $500 $909
10,551
kWh
09 2.4221: Install compressor air intakes in coolest locations $792 $150 $792
9,086
kWh
10 2.2437: Recover waste heat from equipment $2,451 $4,000 $2,451
28,429
kWh
11 2.2522: Isolate hot or cold equipment $1,577 $300 $1,577
18,171
kWh
12 2.7444: Close holes and openings in building such as broken windows $178 $100 $178
2,052
kWh
TOTAL RECOMMENDED $23,541 $23,959 $23,541
271,982
kWh
TOTAL IMPLEMENTED $10,330 $10,112 $10,330
119,285
kWh
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs