ITAC Assessment: AS0040
ITAC logo
ITAC Assessment: AS0040
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product ALUMINUM CANS
NAICS
n/a
SIC 3411: Metal Cans
Sales Range $50
M
to 100
M
# of Employees 111
Plant Area
n/a
Annual Production 1,000,000,000
pieces
Production Hrs. Annual 7,344
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,114,537 17,868,992
kWh
Natural Gas $412,169 99,285
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $300,814 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $300,814

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4133: Use most efficient type of electric motors $2,811 $2,794 $2,811
45,135
kWh
-
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $8,154 - $8,154
130,715
kWh
-
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,134 $2,543 $2,134
34,291
kWh
-
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $9,889 $1,000 $9,889
158,558
kWh
-
05 2.4231: Reduce the pressure of compressed air to the minimum required $12,948 - $12,948
207,503
kWh
-
06 2.4221: Install compressor air intakes in coolest locations $13,041 $500 $13,041
208,968
kWh
-
07 2.4321: Upgrade obsolete equipment $10,456 - $10,456
167,644
kWh
-
08 2.7142: Utilize higher efficiency lamps and/or ballasts $3,777 $555 $3,777
60,668
kWh
-
09 2.7142: Utilize higher efficiency lamps and/or ballasts $537 $776 $537
8,499
kWh
-
10 2.6232: Install set-back timers $3,044 $900 $3,044
48,945
kWh
-
11 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat $190,214 - $344,541
5,524,033
kWh
$(-154,327.0)
-
MMBtu
12 2.1233: Analyze flue gas for proper air/fuel ratio $9,916 $2,500 - $9,916
-
MMBtu
13 2.2511: Insulate bare equipment $33,741 $18,360 - $33,741
-
MMBtu
14 2.2511: Insulate bare equipment $152 $165 - $152
-
MMBtu
TOTAL RECOMMENDED $300,814 $30,093 $411,332
6,594,959
kWh
$(-110,518.0)
-
MMBtu
TOTAL IMPLEMENTED $300,814 $30,093 $411,332
6,594,959
kWh
$(-110,518.0)
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs