Assessment Year | 1991 |
---|---|
Principal Product | ALUMINUM CANS |
NAICS |
n/a
|
SIC | 3411: Metal Cans |
Sales Range | $50 M to 100M |
# of Employees | 111 |
Plant Area |
n/a
|
Annual Production | 1,000,000,000
pieces
|
Production Hrs. Annual | 7,344
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,114,537 | 17,868,992 |
kWh
|
$0.062 |
Natural Gas | $412,169 | 99,285 |
MMBtu
|
$4.15 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $300,814 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $300,814 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $2,811 | $2,794 |
$2,811
45,135
kWh
|
- | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $8,154 | - |
$8,154
130,715
kWh
|
- | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,134 | $2,543 |
$2,134
34,291
kWh
|
- | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $9,889 | $1,000 |
$9,889
158,558
kWh
|
- | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $12,948 | - |
$12,948
207,503
kWh
|
- | |
06 | 2.4221: Install compressor air intakes in coolest locations | $13,041 | $500 |
$13,041
208,968
kWh
|
- | |
07 | 2.4321: Upgrade obsolete equipment | $10,456 | - |
$10,456
167,644
kWh
|
- | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,777 | $555 |
$3,777
60,668
kWh
|
- | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $537 | $776 |
$537
8,499
kWh
|
- | |
10 | 2.6232: Install set-back timers | $3,044 | $900 |
$3,044
48,945
kWh
|
- | |
11 | 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat | $190,214 | - |
$344,541
5,524,033
kWh
|
$(-154,327.0)
-
MMBtu
|
|
12 | 2.1233: Analyze flue gas for proper air/fuel ratio | $9,916 | $2,500 | - |
$9,916
-
MMBtu
|
|
13 | 2.2511: Insulate bare equipment | $33,741 | $18,360 | - |
$33,741
-
MMBtu
|
|
14 | 2.2511: Insulate bare equipment | $152 | $165 | - |
$152
-
MMBtu
|
|
TOTAL RECOMMENDED | $300,814 | $30,093 |
$411,332
6,594,959
kWh
|
$(-110,518.0)
-
MMBtu
|
||
TOTAL IMPLEMENTED | $300,814 | $30,093 |
$411,332
6,594,959
kWh
|
$(-110,518.0)
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs