Assessment Year | 2000 |
---|---|
Principal Product | Steel Pipe Coupling |
NAICS |
n/a
|
SIC | 3498: Fabricated Pipe and Pipe Fittings |
Sales Range | $10 M to 50M |
# of Employees | 125 |
Plant Area |
175,000
ft2
|
Annual Production | 25,000,000
lb
|
Production Hrs. Annual | 5,616
hrs
|
Location (State) | Arkansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $160,822 | 5,592,907 |
kWh
|
$0.029 |
Electricity Demand | $157,918 | 15,689 |
kW-mo/yr
|
$10.07 |
Natural Gas | $41,359 | 8,169 |
MMBtu
|
$5.06 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $516,484 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $19,005 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Product Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,559 | $260 |
$1,534
53,048
kWh
|
$1,025
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $6,930 | - | - |
$6,930
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.2221: Use immersion heating in tanks, melting pots, etc | $16,446 | $15,663 |
$2,419
83,529
kWh
|
$9,663
-
kW-mo/yr
|
- | $4,364 | - | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $768 | $300 |
$419
14,361
kWh
|
$349
-
kW-mo/yr
|
- | - | - | - | |
05 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $3,764 | - | - | - |
$3,764
-
lb
|
- | - | - | |
06 | 4.514: Re-arrange equipment layout to reduce handling costs | $21,267 | $59,881 | - | - | - | - | $21,267 | - | |
07 | 4.652: Replace existing equipment with more suitable substitutes | $464,750 | $385,000 | - | - | - | - | - | $464,750 | |
TOTAL RECOMMENDED | $516,484 | $461,104 |
$4,372
150,938
kWh
|
$17,967
-
kW-mo/yr
|
$3,764
-
lb
|
$4,364 | $21,267 | $464,750 | ||
TOTAL IMPLEMENTED | $19,005 | $15,923 |
$3,953
136,577
kWh
|
$10,688
-
kW-mo/yr
|
- | $4,364 | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Product Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs