ITAC Assessment: AR0184
ITAC logo
ITAC Assessment: AR0184
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Plastic tables and Appliance Parts
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 180
Plant Area 138,000
ft2
Annual Production 1,100,000
lb
Production Hrs. Annual 8,400
hrs
Location (State) Arkansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $46,384 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Product Savings By-product Production Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $544 $413 $53
1,465
kWh
$10
-
kW-mo/yr
- - $481 - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $3,142 $6,340 $2,425
77,667
kWh
$717
-
kW-mo/yr
- - - - -
03 2.4133: Use most efficient type of electric motors $743 $1,378 $591
19,930
kWh
$152
-
kW-mo/yr
- - - - -
04 2.4221: Install compressor air intakes in coolest locations $1,102 $500 $896
31,067
kWh
$206
-
kW-mo/yr
- - - - -
05 3.4116: Meter recycled water (to reduce sewer charges) $10,529 $1,550 - - $10,529
-
Tgal
- - - -
06 3.5315: Lease / purchase baler; sell cardboard to recycler $12,369 $8,000 - - - $12,369
-
lb
- - -
07 4.446: Automate finishing process $13,709 $3,000 - - - - - $13,709 -
08 4.423: Move product using mechanical means $4,246 $9,500 - - - - - - $4,246
TOTAL RECOMMENDED $46,384 $30,681 $3,965
130,129
kWh
$1,085
-
kW-mo/yr
$10,529
-
Tgal
$12,369
-
lb
$481 $13,709 $4,246
TOTAL IMPLEMENTED - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Product Savings By-product Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs