Assessment Year | 2016 |
---|---|
Principal Product | pharmaceuticals |
NAICS | 325412: Pharmaceutical Preparation Manufacturing |
SIC | 2834: Pharmaceutical Preparations |
Sales Range | $50 M to 100M |
# of Employees | 325 |
Plant Area |
348,480
ft2
|
Annual Production | 6,614
units
|
Production Hrs. Annual | 8,568
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $336,082 | 5,491,305 |
kWh
|
$0.061 | |
Electricity Demand | $110,882 | 13,434 |
kW-mo/yr
|
$8.25 | |
Electricity Fees | $48,021 | - |
|
- | |
Natural Gas | $84,970 | 12,822 |
MMBtu
|
$6.63 | |
Waste Disposal Costs | |||||
Other Liquid (haz) | $302,400 | 134,400 |
gal
|
$2.25 | |
TOTAL YEARLY COSTS | $882,355 | ||||
RECOMMENDED SAVINGS* | $458,356 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7243: Improve air circulation with destratification fans / other methods | $9,894 | $5,100 |
$1,017
15,938
kWh
|
- |
$8,877
-
MMBtu
|
- | - | - | |
02 | 3.6124: Burn waste oil for heat | $375,721 | $189,945 | - | - |
$73,321
-
MMBtu
|
$302,400
-
gal
|
- | - | |
03 | 2.6231: Utilize controls to operate equipment only when needed | $39,019 | $15,722 |
$29,956
469,604
kWh
|
- |
$9,063
-
MMBtu
|
- | - | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,352 | $500 |
$1,208
18,933
kWh
|
$144
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.7135: Install occupancy sensors | $4,233 | $5,720 |
$3,181
49,866
kWh
|
- | - | - | $420 | $632 | |
06 | 2.9114: Use solar heat to make electricty | $28,137 | $340,762 |
$28,014
439,167
kWh
|
$123
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $458,356 | $557,749 |
$63,376
993,508
kWh
|
$267
-
kW-mo/yr
|
$91,261
-
MMBtu
|
$302,400
-
gal
|
$420 | $632 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs