Assessment Year | 1999 |
---|---|
Principal Product | Cardboard containers |
NAICS |
n/a
|
SIC | 2653: Corrugated and Solid Fiber Boxes |
Sales Range | $10 M to 50M |
# of Employees | 50 |
Plant Area |
167,000
ft2
|
Annual Production | 6,160,435
pieces
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $58,803 | 1,499,121 |
kWh
|
$0.039 |
Electricity Demand | $35,026 | 3,851 |
kW-mo/yr
|
$9.10 |
Natural Gas | $18,218 | 3,262 |
MMBtu
|
$5.58 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $24,364 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,080 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,867 | $161 |
$5,634
61,547
kWh
|
$3,233
-
kW-mo/yr
|
- | - | - | - | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $271 | $220 |
$102
1,758
kWh
|
$169
-
kW-mo/yr
|
- | - | - | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,348 | $130 |
$649
16,706
kWh
|
$699
-
kW-mo/yr
|
- | - | - | - | - | |
04 | 2.4133: Use most efficient type of electric motors | $149 | $377 |
$61
1,465
kWh
|
$88
-
kW-mo/yr
|
- | - | - | - | - | |
05 | 2.7447: Install vinyl strip / high speed / air curtain doors | $4,553 | $8,938 | - | - | - |
$4,553
-
MMBtu
|
- | - | - | |
06 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $1,472 | - | - | - | $(-2.0) | - |
$1,474
-
lb
|
- | - | |
07 | 3.5311: Recover and reuse waste material | $2,864 | $6,495 | - | - | - | - | - | - | $2,864 | |
08 | 4.625: Develop standard operating procedures | $4,840 | $800 |
$(-47.0)
(-879)
kWh
|
- | - | - | - | $4,887 | - | |
TOTAL RECOMMENDED | $24,364 | $17,121 |
$6,399
80,597
kWh
|
$4,189
-
kW-mo/yr
|
$(-2.0) |
$4,553
-
MMBtu
|
$1,474
-
lb
|
$4,887 | $2,864 | ||
TOTAL IMPLEMENTED | $8,080 | $1,527 |
$765
19,050
kWh
|
$956
-
kW-mo/yr
|
$(-2.0) | - |
$1,474
-
lb
|
$4,887 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs