ITAC Assessment: AR0158
ITAC logo
ITAC Assessment: AR0158
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Hardboard
NAICS
n/a
SIC 2394: Canvas and Related Products
Sales Range $10
M
to 50
M
# of Employees 110
Plant Area 32,500
ft2
Annual Production 133,600
thousand feet
Production Hrs. Annual 8,760
hrs
Location (State) Arkansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $503,513 18,615,475
kWh
Electricity Demand $377,890 36,373
kW-mo/yr
Natural Gas $701,979 284,243
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $118,947 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings Primary Product Savings
01 2.4221: Install compressor air intakes in coolest locations $1,328 $1,000 $905
33,411
kWh
$423
-
kW-mo/yr
- - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,718 $80 $3,744
138,628
kWh
$1,974
-
kW-mo/yr
- - -
03 2.1133: Adjust burners for efficient operation $13,533 $1,000 $13,533
1,605,803
kWh
- - - -
04 2.4133: Use most efficient type of electric motors $10,831 - $183
11,723
kWh
$148
-
kW-mo/yr
- $10,500 -
05 4.126: Install sensors to detect defects $63,302 $6,700 - - - - $63,302
06 4.446: Automate finishing process $24,235 $45,000 - - $24,235 - -
07 4.122: Develop standard procedures to improve internal yields - $2,000 - - - - -
TOTAL RECOMMENDED $118,947 $55,780 $18,365
1,789,565
kWh
$2,545
-
kW-mo/yr
$24,235 $10,500 $63,302
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs