Assessment Year | 1998 |
---|---|
Principal Product | Standard Hex Head Fasteners |
NAICS |
n/a
|
SIC | 3452: Bolts, Nuts, Screws, Rivets, and Washers |
Sales Range | $10 M to 50M |
# of Employees | 109 |
Plant Area |
290,260
ft2
|
Annual Production | 17,832
ton
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Arkansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $304,537 | 10,439,918 |
kWh
|
$0.029 |
Electricity Demand | $152,807 | 22,638 |
kW-mo/yr
|
$6.75 |
Natural Gas | $395,827 | 127,413 |
MMBtu
|
$3.11 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $42,764 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | Water Consumption Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2511: Insulate bare equipment | $1,129 | $464 | - | - |
$1,129
-
MMBtu
|
- | - | - | - | - | - | |
02 | 2.7111: Reduce illumination to minimum necessary levels | $645 | $60 |
$421
14,654
kWh
|
$224
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $986 | $160 |
$743
25,498
kWh
|
$243
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,700 | - |
$2,777
72,392
kWh
|
$923
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
05 | 2.4133: Use most efficient type of electric motors | $2,406 | $8,100 |
$1,806
62,427
kWh
|
$600
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
06 | 3.8142: Distill contaminated solvents for reuse | $2,387 | - |
$(-90.0)
(-879)
kWh
|
- | - | - |
$1,877
-
gal
|
$(-3,000.0) | $3,600 | - | - | |
07 | 3.5131: Recycle white water | $5,032 | - |
$(-58.0)
(-1,465)
kWh
|
- | - |
$2,884
-
Tgal
|
- | - | - |
$2,206
-
Tgal
|
- | |
08 | 4.611: Begin a practice of predictive / preventative maintenance | $26,479 | $19,950 | - | - | - | - | - | $(-21,735.0) | - | - | $48,214 | |
TOTAL RECOMMENDED | $42,764 | $28,734 |
$5,599
172,627
kWh
|
$1,990
-
kW-mo/yr
|
$1,129
-
MMBtu
|
$2,884
-
Tgal
|
$1,877
-
gal
|
$(-24,735.0) | $3,600 |
$2,206
-
Tgal
|
$48,214 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | Water Consumption Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs