Assessment Year | 2024 |
---|---|
Principal Product | Elastomer seals for oilfield use |
NAICS | 339991: Gasket, Packing, and Sealing Device Manufacturing |
SIC | 3053: Gaskets, Packing, and Sealing Devices |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
115,000
ft2
|
Annual Production | 107,000
units
|
Production Hrs. Annual | 5,840
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $838,143 | 11,555,539 |
kWh
|
$0.073 |
Electricity Demand | $233,714 | 26,935 |
kW-mo/yr
|
$8.68 |
Electricity Fees | $103,632 | - |
|
- |
Natural Gas | $53,105 | 13,805 |
MMBtu
|
$3.85 |
TOTAL YEARLY COSTS | $1,228,594 | |||
RECOMMENDED SAVINGS* | $533,098 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.8121: Apply for tax-free status for energy purchases | $439,088 | $15,000 | - | - | $87,818 | $351,270 | |
02 | 2.6231: Utilize controls to operate equipment only when needed | $41,855 | $2,780 |
$41,855
581,320
kWh
|
- | - | - | |
03 | 2.3212: Optimize plant power factor | $37,800 | $99,305 | - |
$37,800
-
kW-mo/yr
|
- | - | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $8,120 | $700 |
$6,275
87,136
kWh
|
$1,845
-
kW-mo/yr
|
- | - | |
05 | 2.4314: Use synthetic lubricant | $2,360 | $90 |
$1,823
25,320
kWh
|
$537
-
kW-mo/yr
|
- | - | |
06 | 2.4221: Install compressor air intakes in coolest locations | $1,915 | $720 |
$1,610
22,340
kWh
|
$305
-
kW-mo/yr
|
- | - | |
07 | 2.7135: Install occupancy sensors | $1,095 | $2,460 |
$1,095
15,185
kWh
|
- | - | - | |
08 | 2.7224: Reduce space conditioning during non-working hours | $865 | $390 |
$720
9,990
kWh
|
$145
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $533,098 | $121,445 |
$53,378
741,291
kWh
|
$40,632
-
kW-mo/yr
|
$87,818 | $351,270 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs