Assessment Year | 1990 |
---|---|
Principal Product | LEAD ACID BATTERIES |
NAICS |
n/a
|
SIC | 3691: Storage Batteries |
Sales Range | $10 M to 50M |
# of Employees | 375 |
Plant Area |
n/a
|
Annual Production | 933,000
pieces
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $519,900 | 10,990,035 |
kWh
|
$0.047 |
Natural Gas | $242,480 | 81,350 |
MMBtu
|
$2.98 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $87,061 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $31,321 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $51,060 | $175,500 |
$89,780
-
kWh
|
- | $(-38,720.0) | |
02 | 2.3212: Optimize plant power factor | $20,490 | $34,000 |
$20,490
-
kWh
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,980 | $900 |
$3,980
131,887
kWh
|
- | - | |
04 | 2.2511: Insulate bare equipment | $3,100 | $115 | - |
$3,100
-
MMBtu
|
- | |
05 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $2,850 | $11,750 |
$2,850
93,787
kWh
|
- | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,330 | $10,500 |
$1,330
33,118
kWh
|
- | - | |
07 | 2.6214: Shut off pilots in standby equipment | $1,980 | $7,700 | - |
$1,980
-
MMBtu
|
- | |
08 | 2.4221: Install compressor air intakes in coolest locations | $970 | $137 |
$970
34,584
kWh
|
- | - | |
09 | 2.6212: Turn off equipment during breaks, reduce operating time | $695 | $700 |
$695
21,395
kWh
|
- | - | |
10 | 2.6232: Install set-back timers | $500 | $1,180 |
$470
10,258
kWh
|
- | $30 | |
11 | 2.3132: Recharge batteries on during off-peak demand periods | $106 | - |
$106
-
kWh
|
- | - | |
TOTAL RECOMMENDED | $87,061 | $242,482 |
$120,671
325,029
kWh
|
$5,080
-
MMBtu
|
$(-38,690.0) | ||
TOTAL IMPLEMENTED | $31,321 | $43,552 |
$26,241
187,866
kWh
|
$5,080
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs