Search Recommendations
ITAC logo
Search Recommendations
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

3,730

matching recommendations
$
$
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC 2+ Digits Required
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
OR0829 #05 Y:2026 Replace existing hvac unit with high efficiency model $11,641 $100,000
OR0829 #04 Y:2026 Use solar heat to make electricty $49,956 $132,300
OR0829 #03 Y:2026 Use adjustable frequency drive or multiple speed motors on existing system $1,322 $8,827
OR0829 #02 Y:2026 Utilize higher efficiency lamps and/or ballasts $3,055 $1,887
OR0829 #01 Y:2026 Utilize energy-efficient belts and other improved mechanisms $510 -
ORC026 #05 Y:2026 Reduce ventilation air $5,887 $35,000
ORC026 #04 Y:2026 Use adjustable frequency drive or multiple speed motors on existing system $725 $2,500
ORC026 #03 Y:2026 Use adjustable frequency drive or multiple speed motors on existing system $3,008 $5,000
ORC026 #02 Y:2026 Install set-back timers $589 $20
ORC026 #01 Y:2026 Utilize controls to operate equipment only when needed $546 -
ORC025 #03 Y:2026 Repair or replace steam traps $6,452 $1,432
ORC025 #02 Y:2026 Utilize higher efficiency lamps and/or ballasts $2,575 $4,361
ORC025 #01 Y:2026 Reduce space conditioning during non-working hours $4,484 -
OR0828 #05 Y:2026 Use solar heat to make electricty $56,750 $1,165,500
OR0828 #04 Y:2026 Optimize plant power factor $2,860 $21,699
OR0828 #03 Y:2026 Modify process to reduce material use/cost $16,306 $10,000
OR0828 #02 Y:2026 Add equipment/ operators to reduce production bottleneck $12,537 $2,000
OR0828 #01 Y:2026 Eliminate or reduce compressed air usage $5,700 $50
OR0827 #07 Y:2026 Use solar heat to make electricty $34,776 $600,754
OR0827 #06 Y:2026 Optimize plant power factor $7,574 $55,435