ITAC Assessment: OR0538
ITAC logo
ITAC Assessment: OR0538
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product Frozen pizzas, Canned goods
NAICS 424420: Packaged Frozen Food Merchant Wholesalers
SIC 5142: Packaged Frozen Foods
Sales Range $100
M
to 500
M
# of Employees 550
Plant Area 170,000
ft2
Annual Production 31,000,000
units
Production Hrs. Annual 1,664
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $478,431 22,194
kWh
Natural Gas $721,064 779,267
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $720,443 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Natural Gas Savings Other Energy Savings Primary Product Savings Increase in Production Savings
01 4.131: Modify process to reduce material use/cost $113,818 $1,600 - - - $113,818
02 2.2515: Use optimum thickness insulation $15,451 $3,248 $15,451
-
MMBtu
- - -
03 4.131: Modify process to reduce material use/cost $433,305 $300,000 - - $433,305 -
04 4.126: Install sensors to detect defects $132,288 $140,000 - - $132,288 -
05 2.2449: Recover heat from exhausted steam, hot air or hot water $9,546 $7,085 - $9,546
-
MMBtu
- -
06 2.2449: Recover heat from exhausted steam, hot air or hot water $16,035 $16,204 - $16,035
-
MMBtu
- -
TOTAL RECOMMENDED $720,443 $468,137 $15,451
-
MMBtu
$25,581
-
MMBtu
$565,593 $113,818
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Natural Gas Savings Other Energy Savings Primary Product Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs