ITAC Assessment: UK2005
ITAC logo
ITAC Assessment: UK2005
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2021
Principal Product Distilled Spirits
NAICS 312140: Distilleries
SIC 2085: Distilled and Blended Liquors
Sales Range $50
M
to 100
M
# of Employees 100
Plant Area 30,000
ft2
Annual Production 7,306,895
units
Production Hrs. Annual 8,400
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $328,497 5,518,455
kWh
Electricity Demand $91,503 11,840
kW-mo/yr
Natural Gas $629,091 215,465
MMBtu
Other Gas $18,086 1
MMBtu
Waste Disposal Costs
Water Usage $189,600 68,595
Tgal
Water Disposal $64,479 9,224
Tgal
TOTAL YEARLY COSTS $1,321,256
RECOMMENDED SAVINGS* $120,964 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4222: Install adequate dryers on air lines to eliminate blowdown $2,303 $5,660 $2,303
38,388
kWh
- -
02 2.4231: Reduce the pressure of compressed air to the minimum required $802 - $802
13,373
kWh
- -
03 2.7231: Use radiant heater for spot heating $5,104 $3,740 - - $5,104
-
MMBtu
04 2.4224: Upgrade controls on compressors $9,505 $5,250 $8,029
133,812
kWh
$1,476
-
kW-mo/yr
-
05 2.7224: Reduce space conditioning during non-working hours $6,176 $80 $6,176
102,938
kWh
- -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $4,065 $3,580 $3,338
55,636
kWh
$727
-
kW-mo/yr
-
07 2.1233: Analyze flue gas for proper air/fuel ratio $21,605 $3,000 - - $21,605
-
MMBtu
08 2.2442: Preheat combustion air with waste heat $66,411 $240,000 - - $66,411
-
MMBtu
09 2.2511: Insulate bare equipment $4,993 $6,721 - - $4,993
-
MMBtu
TOTAL RECOMMENDED $120,964 $268,031 $20,648
344,147
kWh
$2,203
-
kW-mo/yr
$98,113
-
MMBtu
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs