Assessment Year | 2023 |
---|---|
Principal Product | Chemical product |
NAICS | 325998: All Other Miscellaneous Chemical Product and Preparation Manufacturing |
SIC | 2819: Industrial Inorganic Chemicals, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 57 |
Plant Area |
99,250
ft2
|
Annual Production | 15,492,415
lb
|
Production Hrs. Annual | 2,125
hrs
|
Location (State) | Connecticut |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $17,715 | 433,488 |
kWh
|
$0.041 | |
Electricity Demand | $31,649 | 1,697 |
kW-mo/yr
|
$18.65 | |
Electricity Fees | $20,189 | - |
|
- | |
Natural Gas | $39,743 | 3,214 |
MMBtu
|
$12.37 | |
LPG | $3,359 | 75 |
MMBtu
|
$44.67 | |
Fuel Oil #4 | $24,708 | 837 |
MMBtu
|
$29.51 | |
Waste Disposal Costs | |||||
Water Usage | $2,722 | 768 |
Tgal
|
$3.54 | |
Water Disposal | $3,834 | 726 |
Tgal
|
$5.28 | |
TOTAL YEARLY COSTS | $143,920 | ||||
RECOMMENDED SAVINGS* | $37,715 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Fuel Oil #2 Savings | Fuel Oil #4 Savings | Water Usage Savings | Water Disposal Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.8121: Apply for tax-free status for energy purchases | $12,379 | - | - | - | $12,379 | - | - | - | - | - | - | |
02 | 2.3192: Use fossil fuel powered generator during peak demand periods | $4,994 | - |
$151
3,696
kWh
|
$1,436
-
kW-mo/yr
|
$4,670 | - |
$(-1,263.4)
-
MMBtu
|
- | - | - | - | |
03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $352 | - | - | - | - |
$832
-
MMBtu
|
- | - | - | - | $(-480.0) | |
04 | 2.1224: Replace boiler | $6,269 | $41,061 | - | - | - |
$6,269
-
MMBtu
|
- | - | - | - | - | |
05 | 2.2136: Install / repair insulation on steam lines | $508 | $529 | - | - | - |
$508
-
MMBtu
|
- | - | - | - | - | |
06 | 2.7232: Replace existing hvac unit with high efficiency model | $411 | $3,486 |
$253
6,192
kWh
|
$158
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
07 | 3.4114: Replace city water with recycled water via cooling tower | $3,643 | $34,992 |
$(-517.3)
(-12,647)
kWh
|
$(-323.1)
-
kW-mo/yr
|
- | - | - | - |
$1,799
-
Tgal
|
$2,684
-
Tgal
|
- | |
08 | 3.4155: Meter waste water | $383 | $455 | - | - | - | - | - | - | - |
$383
-
Tgal
|
- | |
09 | 2.7447: Install vinyl strip / high speed / air curtain doors | $6,108 | $31,637 |
$(-531.8)
(-13,003)
kWh
|
$(-1,369.4)
-
kW-mo/yr
|
- |
$8,010
-
MMBtu
|
- | - | - | - | - | |
10 | 2.1332: Convert combustion equipment to burn natural gas | $2,667 | $13,200 | - | - | - |
$(-1,923.6)
-
MMBtu
|
- |
$4,590
-
MMBtu
|
- | - | - | |
TOTAL RECOMMENDED | $37,715 | $125,360 |
$(-644.7)
(-15,762)
kWh
|
$(-98.3)
-
kW-mo/yr
|
$17,049 |
$13,695
-
MMBtu
|
$(-1,263.4)
-
MMBtu
|
$4,590
-
MMBtu
|
$1,799
-
Tgal
|
$3,067
-
Tgal
|
$(-480.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Fuel Oil #2 Savings | Fuel Oil #4 Savings | Water Usage Savings | Water Disposal Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs