Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

91

matching recommendations
$
$
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Refuse systems
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
UU0250 #06 Y:2024 Turn off equipment during breaks, reduce operating time $6,753 $5,720
UU0250 #05 Y:2024 Utilize higher efficiency lamps and/or ballasts $6,806 $13,208
UU0250 #04 Y:2024 Eliminate or reduce compressed air usage $8,795 $5,760
UU0250 #03 Y:2024 Burn a less expensive grade of fuel $11,024 $16,000
UU0250 #02 Y:2024 Use adjustable frequency drive or multiple speed motors on existing system $18,742 $49,723
UU0250 #01 Y:2024 Optimize plant power factor $42,332 $60,420
IP0183 #04 Y:2023 Optimize plant power factor $71,584 $212,913
IP0183 #03 Y:2023 Use radiant heater for spot heating $8,695 $19,367
IP0183 #02 Y:2023 Increase amount of condensate returned $48,374 $55,000
IP0183 #01 Y:2023 Utilize higher efficiency lamps and/or ballasts $43,443 $37,653
AM0849 #11 Y:2022 Use solar heat to make electricty $71,703 $867,640
AM0849 #10 Y:2022 Reduce the pressure of compressed air to the minimum required $362 $30
AM0849 #09 Y:2022 Eliminate leaks in inert gas and compressed air lines/ valves $7,245 $1,000
AM0849 #08 Y:2022 Utilize higher efficiency lamps and/or ballasts $535 $830
AM0849 #07 Y:2022 Repair or replace steam traps $6,765 $560
AM0849 #06 Y:2022 Pay utility bills on time $344 -
AM0849 #05 Y:2022 Install occupancy sensors $3,395 $1,530
AM0849 #04 Y:2022 Use adjustable frequency drive or multiple speed motors on existing system $18,625 $37,000
AM0849 #03 Y:2022 Adopt in-house material generation $15,440 $21,500
AM0849 #02 Y:2022 Increase amount of condensate returned $1,157 $360