matching recommendations| ID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
|---|---|---|---|---|---|---|
| SU0588 #12 Y:2025 | 12 | 2025 | Use solar heat to make electricty | $50,535 | $467,049 |
n/a
|
| SU0588 #11 Y:2025 | 11 | 2025 | Implement a regular maintenance program to reduce emissions from leaky valves and pipe fittings | $377 | $1,928 |
n/a
|
| SU0588 #10 Y:2025 | 10 | 2025 | Install back-up equipment | $30,784 | $86,000 |
n/a
|
| SU0588 #09 Y:2025 | 09 | 2025 | Install occupancy sensors | $1,049 | $2,285 |
n/a
|
| SU0588 #08 Y:2025 | 08 | 2025 | Conserve energy by efficient use of vending machines | $232 | $368 |
n/a
|
| SU0588 #07 Y:2025 | 07 | 2025 | Utilize higher efficiency lamps and/or ballasts | $1,289 | $1,441 |
n/a
|
| SU0588 #06 Y:2025 | 06 | 2025 | Use or replace with energy efficient substitutes | $422 | $461 |
n/a
|
| SU0588 #05 Y:2025 | 05 | 2025 | Install compressor air intakes in coolest locations | $559 | $471 |
n/a
|
| SU0588 #04 Y:2025 | 04 | 2025 | Eliminate leaks in inert gas and compressed air lines/ valves | $1,258 | $209 |
n/a
|
| SU0588 #03 Y:2025 | 03 | 2025 | Use or replace with energy efficient substitutes | $914 | $74 |
n/a
|
| SU0588 #02 Y:2025 | 02 | 2025 | Reduce space conditioning during non-working hours | $775 | - |
n/a
|
| SU0588 #01 Y:2025 | 01 | 2025 | Reschedule plant operations or reduce load to avoid peaks | $2,279 | - |
n/a
|
| UU0288 #05 Y:2025 | 05 | 2025 | Eliminate or reduce compressed air usage | $2,025 | $6,732 |
n/a
|
| UU0288 #04 Y:2025 | 04 | 2025 | Recover waste heat from equipment | $832 | $5,310 |
n/a
|
| UU0288 #03 Y:2025 | 03 | 2025 | Recover waste heat from equipment | $15,325 | $47,180 |
n/a
|
| UU0288 #02 Y:2025 | 02 | 2025 | Reschedule plant operations or reduce load to avoid peaks | $9,190 | $15,750 |
n/a
|
| UU0288 #01 Y:2025 | 01 | 2025 | Install an uninteruptable power supply | $915,000 | $1,225,000 |
n/a
|
| OK1161 #04 Y:2025 | 04 | 2025 | Redesign process | $57,400 | $29,297 |
n/a
|
| OK1161 #03 Y:2025 | 03 | 2025 | Use adjustable frequency drive or multiple speed motors on existing system | $3,661 | $3,410 |
n/a
|
| OK1161 #02 Y:2025 | 02 | 2025 | Eliminate leaks in inert gas and compressed air lines/ valves | $5,351 | $3,460 |