1,223
matching recommendations
$
$
| ARC | 2+ Digits Required | |
| NAICS | 3+ Digits Required | |
| SIC | Coating, engraving, and allied services, not elsewhere classified | |
| 3+ Characters Required for Products | ||
| ID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
|---|---|---|---|---|---|---|
| UD1139 #06 Y:2026 | 06 | 2026 | Optimize plant power factor | $7,031 | $18,291 |
n/a
|
| UD1139 #05 Y:2026 | 05 | 2026 | Utilize higher efficiency lamps and/or ballasts | $11,899 | $20,626 |
n/a
|
| UD1139 #04 Y:2026 | 04 | 2026 | Re-use or recycle hot or cold process exhaust air | $38,983 | $15,000 |
n/a
|
| UD1139 #03 Y:2026 | 03 | 2026 | Install compressor air intakes in coolest locations | $3,681 | $4,800 |
n/a
|
| UD1139 #02 Y:2026 | 02 | 2026 | Reduce the pressure of compressed air to the minimum required | $4,391 | - |
n/a
|
| UD1139 #01 Y:2026 | 01 | 2026 | Eliminate leaks in inert gas and compressed air lines/ valves | $8,028 | $1,000 |
n/a
|
| SU0595 #10 Y:2026 | 10 | 2026 | Use closed cycle process to minimize waste water production | $15,738 | $185,000 |
n/a
|
| SU0595 #09 Y:2026 | 09 | 2026 | Convert to indirect temperature control system | $4,376 | $43,750 |
n/a
|
| SU0595 #08 Y:2026 | 08 | 2026 | Install desiccant humidity control system | $786 | $4,570 |
n/a
|
| SU0595 #07 Y:2026 | 07 | 2026 | Recover waste heat from equipment | $40 | $208 |
n/a
|
| SU0595 #06 Y:2026 | 06 | 2026 | Conserve energy by efficient use of vending machines | $190 | $568 |
n/a
|
| SU0595 #05 Y:2026 | 05 | 2026 | Eliminate leaks in inert gas and compressed air lines/ valves | $502 | $105 |
n/a
|
| SU0595 #04 Y:2026 | 04 | 2026 | Use or replace with energy efficient substitutes | $1,372 | $119 |
n/a
|
| SU0595 #03 Y:2026 | 03 | 2026 | Apply for tax-free status for energy purchases | $8,965 | $65 |
n/a
|
| SU0595 #02 Y:2026 | 02 | 2026 | Reschedule plant operations or reduce load to avoid peaks | $2,928 | - |
n/a
|
| SU0595 #01 Y:2026 | 01 | 2026 | Eliminate or reduce compressed air usage | $339 | - |
n/a
|
| TT0353 #11 Y:2026 | 11 | 2026 | Eliminate leaks in inert gas and compressed air lines/ valves | $666 | $1,520 |
n/a
|
| TT0353 #10 Y:2026 | 10 | 2026 | Upgrade controls on compressors | $2,152 | $5,000 |
n/a
|
| TT0353 #09 Y:2026 | 09 | 2026 | Use waste heat from hot flue gases to preheat | $28,283 | $60,000 |
n/a
|
| TT0353 #08 Y:2026 | 08 | 2026 | Optimize plant power factor | $3,128 | $9,435 |
n/a
|