Search Recommendations
ITAC logo
Search Recommendations
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

5,922

matching recommendations
$
$
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Stone, clay, glass, and concrete products
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
OR0837 #07 Y:2026 Use solar heat to make electricty $30,170 $735,960
OR0837 #06 Y:2026 Adopt in-house material generation $6,766 $68,142
OR0837 #05 Y:2026 Maintain air filters by cleaning or replacement $8,393 $10,000
OR0837 #04 Y:2026 Replace treated water with well / surface water $8,249 $6,786
OR0837 #03 Y:2026 Use flow control valves on equipment to optimize water use $79,017 $25,616
OR0837 #02 Y:2026 Use or replace with energy efficient substitutes $1,500 -
OR0837 #01 Y:2026 Turn off equipment during breaks, reduce operating time $36,378 -
UU0312 #05 Y:2026 Replace fossil fuel equipment with electrical equipment $30,000 $139,500
UU0312 #04 Y:2026 Level zero – install control systems for existing equipment $157,000 $650,000
UU0312 #03 Y:2026 Re-use or recycle hot or cold process exhaust air $12,500 $41,270
UU0312 #02 Y:2026 Insulate bare equipment $11,840 $7,940
UU0312 #01 Y:2026 Modify process to reduce material use/cost $7,200 $4,635
UU0311 #06 Y:2026 Adjust / maintain fork lift trucks for most efficient operation $11,150 $93,000
UU0311 #05 Y:2026 Insulate bare equipment $1,230 $2,350
UU0311 #04 Y:2026 Reduce or eliminate waste $3,600 $4,640
UU0311 #03 Y:2026 Use waste heat from hot flue gases to preheat $13,900 $41,300
UU0311 #02 Y:2026 Use / purchase optimum sized compressor $9,400 $40,200
UU0311 #01 Y:2026 Install system to collect scrap $279,000 $750,000
UU0310 #04 Y:2026 Reduce the pressure of compressed air to the minimum required $350 $800
UU0310 #03 Y:2026 Recover waste heat from equipment $850 $3,540