ITAC Assessment: AT0042
ITAC logo
ITAC Assessment: AT0042
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1986
Principal Product BRICKS
NAICS
n/a
SIC 3251: Brick and Structural Clay Tile
Sales Range $1
M
to 5
M
# of Employees 50
Plant Area
n/a
Annual Production 30,000,000
pieces
Production Hrs. Annual 2,080
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $165,868 2,961,606
kWh
Natural Gas $77,106 14,075
MMBtu
Other Energy $398,522 137,813
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $9,773 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,669

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4133: Use most efficient type of electric motors $662 $409 $662
12,016
kWh
- -
02 2.2511: Insulate bare equipment $104 $100 - $104
-
MMBtu
-
03 2.4312: Improve lubrication practices $8,847 - $11,057
197,538
kWh
- $(-2,210.0)
04 2.4221: Install compressor air intakes in coolest locations $160 $150 $160
2,931
kWh
- -
TOTAL RECOMMENDED $9,773 $659 $11,879
212,485
kWh
$104
-
MMBtu
$(-2,210.0)
TOTAL IMPLEMENTED $9,669 $559 $11,879
212,485
kWh
- $(-2,210.0)
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs