| Assessment Year | 1998 |
|---|---|
| Principal Product | Automotive Stampings |
| NAICS |
n/a
|
| SIC | 3465: Automotive Stampings |
| Sales Range | $10 M to 50M |
| # of Employees | 160 |
| Plant Area |
208,000
ft2
|
| Annual Production | 300,000
units
|
| Production Hrs. Annual | 4,160
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $192,211 | 6,495,604 |
kWh
|
$0.030 |
| Electricity Demand | $274,385 | 17,304 |
kW-mo/yr
|
$15.86 |
| Electricity Fees | $9,880 | - |
|
- |
| Natural Gas | $47,120 | 23,279 |
MMBtu
|
$2.02 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $49,082 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $18,491 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Other Liquid (haz) Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,866 | $14,437 |
$1,200
40,445
kWh
|
$1,666
-
kW-mo/yr
|
- | - | - | - | |
| 02 | 2.7231: Use radiant heater for spot heating | $20,994 | $33,960 | - | - |
$20,994
-
MMBtu
|
- | - | - | |
| 03 | 3.4154: Eliminate leaks in water lines and valves | $1,171 | $600 | - | - | - | - |
$1,171
-
gal
|
- | |
| 04 | 3.4154: Eliminate leaks in water lines and valves | $8,426 | $642 | - | - | - |
$1,648
-
gal
|
$6,778
-
gal
|
- | |
| 05 | 4.122: Develop standard procedures to improve internal yields | $15,625 | $58,992 | - | - | - | - | - | $15,625 | |
| TOTAL RECOMMENDED | $49,082 | $108,631 |
$1,200
40,445
kWh
|
$1,666
-
kW-mo/yr
|
$20,994
-
MMBtu
|
$1,648
-
gal
|
$7,949
-
gal
|
$15,625 | ||
| TOTAL IMPLEMENTED | $18,491 | $73,429 |
$1,200
40,445
kWh
|
$1,666
-
kW-mo/yr
|
- | - | - | $15,625 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs