ITAC Assessment: UM0105
ITAC logo
ITAC Assessment: UM0105
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Automotive Stampings
NAICS
n/a
SIC 3465: Automotive Stampings
Sales Range $10
M
to 50
M
# of Employees 160
Plant Area 208,000
ft2
Annual Production 300,000
units
Production Hrs. Annual 4,160
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $192,211 6,495,604
kWh
Electricity Demand $274,385 17,304
kW-mo/yr
Electricity Fees $9,880 -
Natural Gas $47,120 23,279
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $49,082 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $18,491

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Other Liquid (haz) Savings Primary Product Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,866 $14,437 $1,200
40,445
kWh
$1,666
-
kW-mo/yr
- - - -
02 2.7231: Use radiant heater for spot heating $20,994 $33,960 - - $20,994
-
MMBtu
- - -
03 3.4154: Eliminate leaks in water lines and valves $1,171 $600 - - - - $1,171
-
gal
-
04 3.4154: Eliminate leaks in water lines and valves $8,426 $642 - - - $1,648
-
gal
$6,778
-
gal
-
05 4.122: Develop standard procedures to improve internal yields $15,625 $58,992 - - - - - $15,625
TOTAL RECOMMENDED $49,082 $108,631 $1,200
40,445
kWh
$1,666
-
kW-mo/yr
$20,994
-
MMBtu
$1,648
-
gal
$7,949
-
gal
$15,625
TOTAL IMPLEMENTED $18,491 $73,429 $1,200
40,445
kWh
$1,666
-
kW-mo/yr
- - - $15,625
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs