Assessment Year | 1986 |
---|---|
Principal Product | BRICKS |
NAICS |
n/a
|
SIC | 3251: Brick and Structural Clay Tile |
Sales Range | $1 M to 5M |
# of Employees | 60 |
Plant Area |
n/a
|
Annual Production | 30,000,000
pieces
|
Production Hrs. Annual | 2,600
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $173,244 | 2,916,764 |
kWh
|
$0.059 |
Natural Gas | $722,368 | 131,400 |
MMBtu
|
$5.50 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $13,578 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $12,621 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $853 | $3,046 |
$853
14,361
kWh
|
- | |
02 | 2.2511: Insulate bare equipment | $957 | $150 | - |
$957
-
MMBtu
|
|
03 | 2.4312: Improve lubrication practices | $11,298 | - |
$11,298
190,211
kWh
|
- | |
04 | 2.4221: Install compressor air intakes in coolest locations | $470 | $150 |
$470
7,913
kWh
|
- | |
TOTAL RECOMMENDED | $13,578 | $3,346 |
$12,621
212,485
kWh
|
$957
-
MMBtu
|
||
TOTAL IMPLEMENTED | $12,621 | $3,196 |
$12,621
212,485
kWh
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs