ITAC Assessment: AT0043
ITAC logo
ITAC Assessment: AT0043
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1986
Principal Product BRICKS
NAICS
n/a
SIC 3251: Brick and Structural Clay Tile
Sales Range $1
M
to 5
M
# of Employees 60
Plant Area
n/a
Annual Production 30,000,000
pieces
Production Hrs. Annual 2,600
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $173,244 2,916,764
kWh
Natural Gas $722,368 131,400
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $13,578 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $12,621

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4133: Use most efficient type of electric motors $853 $3,046 $853
14,361
kWh
-
02 2.2511: Insulate bare equipment $957 $150 - $957
-
MMBtu
03 2.4312: Improve lubrication practices $11,298 - $11,298
190,211
kWh
-
04 2.4221: Install compressor air intakes in coolest locations $470 $150 $470
7,913
kWh
-
TOTAL RECOMMENDED $13,578 $3,346 $12,621
212,485
kWh
$957
-
MMBtu
TOTAL IMPLEMENTED $12,621 $3,196 $12,621
212,485
kWh
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs