ARC | 2+ Digits Required | |
NAICS | 3+ Digits Required | |
SIC | Tires and inner tubes | |
3+ Characters Required for Products |
ID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
---|---|---|---|---|---|---|
MZ0189 #06 Y:2015 | 06 | 2015 | Lower temperature during the winter season and vice-versa | $1,139 | - | |
MZ0189 #05 Y:2015 | 05 | 2015 | Eliminate or reduce compressed air usage | $3,835 | $5,500 | |
MZ0189 #04 Y:2015 | 04 | 2015 | Eliminate leaks in inert gas and compressed air lines/ valves | $1,865 | $880 | |
MZ0189 #03 Y:2015 | 03 | 2015 | Install compressor air intakes in coolest locations | $1,216 | $2,500 | |
MZ0189 #02 Y:2015 | 02 | 2015 | Improved material handling (mixing and transfer) | $4,178 | $8,000 | |
MZ0189 #01 Y:2015 | 01 | 2015 | Reschedule plant operations or reduce load to avoid peaks | $18,361 | - | |
WI0096 #10 Y:1990 | 10 | 1990 | Insulate bare equipment | $152 | $352 | |
WI0096 #09 Y:1990 | 09 | 1990 | Install set-back timers | $160 | $400 | |
WI0096 #08 Y:1990 | 08 | 1990 | Utilize higher efficiency lamps and/or ballasts | $24 | $14 | |
WI0096 #07 Y:1990 | 07 | 1990 | Utilize energy-efficient belts and other improved mechanisms | $449 | $1,744 | |
WI0096 #06 Y:1990 | 06 | 1990 | Analyze flue gas for proper air/fuel ratio | $560 | $500 | |
WI0096 #05 Y:1990 | 05 | 1990 | Reduce hot water temperature to the minimum required | $563 | - | |
WI0096 #04 Y:1990 | 04 | 1990 | Recharge batteries on during off-peak demand periods | $5,068 | $800 | |
WI0096 #03 Y:1990 | 03 | 1990 | Improve air circulation with destratification fans / other methods | $8,473 | $3,895 | |
WI0096 #02 Y:1990 | 02 | 1990 | Reschedule plant operations or reduce load to avoid peaks | $27,714 | - | |
WI0096 #01 Y:1990 | 01 | 1990 | Burn fossil fuel to produce steam to drive a steam turbine-generator and use steam exhaust for heat | $77,488 | $400,000 |