ITAC Assessment: TT0325
ITAC logo
ITAC Assessment: TT0325
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product tire bladders
NAICS 326211: Tire Manufacturing (except Retreading)
SIC 3011: Tires and Inner Tubes
Sales Range $10
M
to 50
M
# of Employees 84
Plant Area 164,642
ft2
Annual Production 120,000
units
Production Hrs. Annual 8,000
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $633,750 7,995,200
kWh
Electricity Demand $55,639 9,658
kW-mo/yr
Natural Gas $143,535 38,377
MMBtu
LPG $16,490 695
MMBtu
Waste Disposal Costs
Water Usage $35,662 24,665
Tgal
Water Disposal $43,035 24,665
Tgal
TOTAL YEARLY COSTS $928,111
RECOMMENDED SAVINGS* $377,637 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Usage Savings Water Disposal Savings Ancillary Material Cost Savings
01 2.3413: Burn fossil fuel to produce steam to drive a steam turbine-generator and use steam exhaust for heat $242,348 $1,045,217 $403,119
5,102,772
kWh
- $(-64,750.0)
-
MMBtu
- - $(-96,021.0)
02 2.1223: Install smaller boiler (increase high fire duty cycle) $68,822 $200,000 - - $65,206
-
MMBtu
$3,616
-
Tgal
- -
03 2.2441: Preheat boiler makeup water with waste process heat $30,978 $17,480 $11,321
143,129
kWh
- $19,657
-
MMBtu
- - -
04 2.1243: Use heat from boiler blowdown to preheat boiler feed water $8,824 $22,500 - - $8,768
-
MMBtu
$56
-
Tgal
- -
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $5,974 $16,000 $5,392
68,000
kWh
$582
-
kW-mo/yr
- - - -
06 2.6218: Turn off equipment when not in use $5,854 $400 $5,854
73,825
kWh
- - - - -
07 2.4239: Eliminate or reduce compressed air usage $5,049 $30,040 $5,049
63,669
kWh
- - - - -
08 2.7135: Install occupancy sensors $4,068 $15,000 $4,068
51,300
kWh
- - - - -
09 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $3,955 $1,000 $3,569
45,000
kWh
$386
-
kW-mo/yr
- - - -
10 3.4155: Meter waste water $1,047 $1,100 - - - - $1,047
-
Tgal
-
11 2.4133: Use most efficient type of electric motors $718 $2,640 $650
8,208
kWh
$68
-
kW-mo/yr
- - - -
TOTAL RECOMMENDED $377,637 $1,351,377 $439,022
5,555,903
kWh
$1,036
-
kW-mo/yr
$28,881
-
MMBtu
$3,672
-
Tgal
$1,047
-
Tgal
$(-96,021.0)
TOTAL IMPLEMENTED - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Usage Savings Water Disposal Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs