Assessment Year | 2024 |
---|---|
Principal Product | tire bladders |
NAICS | 326211: Tire Manufacturing (except Retreading) |
SIC | 3011: Tires and Inner Tubes |
Sales Range | $10 M to 50M |
# of Employees | 84 |
Plant Area |
164,642
ft2
|
Annual Production | 120,000
units
|
Production Hrs. Annual | 8,000
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $633,750 | 7,995,200 |
kWh
|
$0.079 | |
Electricity Demand | $55,639 | 9,658 |
kW-mo/yr
|
$5.76 | |
Natural Gas | $143,535 | 38,377 |
MMBtu
|
$3.74 | |
LPG | $16,490 | 695 |
MMBtu
|
$23.73 | |
Waste Disposal Costs | |||||
Water Usage | $35,662 | 24,665 |
Tgal
|
$1.45 | |
Water Disposal | $43,035 | 24,665 |
Tgal
|
$1.74 | |
TOTAL YEARLY COSTS | $928,111 | ||||
RECOMMENDED SAVINGS* | $377,637 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3413: Burn fossil fuel to produce steam to drive a steam turbine-generator and use steam exhaust for heat | $242,348 | $1,045,217 |
$403,119
5,102,772
kWh
|
- |
$(-64,750.0)
-
MMBtu
|
- | - | $(-96,021.0) | |
02 | 2.1223: Install smaller boiler (increase high fire duty cycle) | $68,822 | $200,000 | - | - |
$65,206
-
MMBtu
|
$3,616
-
Tgal
|
- | - | |
03 | 2.2441: Preheat boiler makeup water with waste process heat | $30,978 | $17,480 |
$11,321
143,129
kWh
|
- |
$19,657
-
MMBtu
|
- | - | - | |
04 | 2.1243: Use heat from boiler blowdown to preheat boiler feed water | $8,824 | $22,500 | - | - |
$8,768
-
MMBtu
|
$56
-
Tgal
|
- | - | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,974 | $16,000 |
$5,392
68,000
kWh
|
$582
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.6218: Turn off equipment when not in use | $5,854 | $400 |
$5,854
73,825
kWh
|
- | - | - | - | - | |
07 | 2.4239: Eliminate or reduce compressed air usage | $5,049 | $30,040 |
$5,049
63,669
kWh
|
- | - | - | - | - | |
08 | 2.7135: Install occupancy sensors | $4,068 | $15,000 |
$4,068
51,300
kWh
|
- | - | - | - | - | |
09 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,955 | $1,000 |
$3,569
45,000
kWh
|
$386
-
kW-mo/yr
|
- | - | - | - | |
10 | 3.4155: Meter waste water | $1,047 | $1,100 | - | - | - | - |
$1,047
-
Tgal
|
- | |
11 | 2.4133: Use most efficient type of electric motors | $718 | $2,640 |
$650
8,208
kWh
|
$68
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $377,637 | $1,351,377 |
$439,022
5,555,903
kWh
|
$1,036
-
kW-mo/yr
|
$28,881
-
MMBtu
|
$3,672
-
Tgal
|
$1,047
-
Tgal
|
$(-96,021.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs